Specifications al City of Tigard TIGARD Responses by Caleb Cox are added in red below. April 5, 2023 RE: Kitchen addition / remodel Project Information Building Permit: MST2023-00120 Construction Type:VB Address: 14165 SW 103rd Ave Occupancy Types: R3 Area: Stories: 1 The plan review was performed under the Oregon Residential Specialty Code (ORSC) 2021 edition. The submitted plans have been reviewed and the following information is required prior to issuance of the permit. Codes can be referenced online at https://www.oregon.gov/bcd/codes- stand/Pages/index.aspx. 1. The plan shows a Glulam of 14'and the kitchen opening appears to be 22'. Provide beam calc for entire span and show support locations and size on plan.This beam will not span the full 22'width.There will be a bearing wall resting on the foundation mid-span that makes the effective span 14'. See sheet 06. 2. Show post supports in all locations. Check near garage.Added sheet 11 to show all post supports for each beam. Structural calculations are also included for each post (Note: some are made up of multiple 2x4s stacked together). 3. Call out blocking or show in cut view blocking between floors. (Squash blocks).Sheet 11— Added callouts for blocking adjacent to floor joists between floors. 4. Provide continuous load path.The 6x6 post must come down on equal size member below. R601.20.Sheet 11—Added cross-section details to show continuous load path to foundation. Per the conversation I had with Allyson, I am electing to have the 6x6 posts be supported by the existing 2x4 bearing wall in the basement.The 2x4 wall will be reinforced with additional blocking and I've included structural calculations for all proposed posts/bearing walls to justify this change from the typical design approach. 5. Provide uplift resistance per R802.8. Sheet 06—Added callout for Simpson Strong Tie H1A connectors at the rafter to top plate connection and RR connectors at the rafter to ridge r board connection. 6. Show or call out lateral supports for roof framing per R802.8.Sheet 07—Added callout to install 2x6 blocking between rafters. 7. Call out required Shear wall nailing 6"edge and 12"field TYP. Sheet 07—Added to existing wall bracing callout to clarify fastening every 6" at edges and 12" field. Please let me know if you have any questions. Thank you, Allyson Armstrong 503-718-8137 Boise C BC CALC® Member Report PASSED ENGINEERED WOOD PRODUCTS Build 16959 April 10, 2023 22:03:33 Job name: 14165 Kitchen Addition File name: Beam Calculations Address: Specifier: City, State,Zip: Designer: Caleb Cox Customer: Company: Code reports: WCLIB/WWPA, PR-L313 Member Summary Design Description Results Product Plies Control Design Beam 1 Passed 5-1/8"x 12"BOISE GLULAM®24F-V4/DF 1 Total Load Deflection 71.9% (Living Room) Beam 2 Passed 5-1/8"x 7-1/2"BOISE GLULAM®24F-V4/DF 1 Pos. Moment 30.2% (Hall) Beam 3 Passed 5-1/8"x 7-1/2"BOISE GLULAM®24F-V4/DF 1 Member Bearing(1)9.3% (Stairs) Beam 4 Passed 5-1/8"x 7-1/2"BOISE GLULAM®24F-V4/DF 1 Total Load Deflection 87.8% (Kitchen) Post 1 Passed 2 x 4 DFL SS 3 Slenderness Ratio 54.9% Post 10 Passed 2 x 4 DFL SS 2 Slenderness Ratio 64.0% Post 2 Passed 5-1/8"x 5-1/2"BOISE GLULAM®24F-V4/DF 1 Slenderness Ratio 37.5% Post 3 Passed 2 x 4 DFL SS 4 Axial Compression and Bending Front-Back 57.4% Post 4 Passed 2 x 4 DFL SS 4 Axial Compression and Bending Front-Back 64.9% Post 5 Passed 5-1/8"x 5-1/2"BOISE GLULAM®24F-V4/DF 1 Slenderness Ratio 37.5% Post 6 Passed 2 x 4 DFL SS 2 Slenderness Ratio 64.0% Post 7 Passed 2 x 4 DFL SS 3 Slenderness Ratio 54.9% Post 8 Passed 2 x 4 DFL SS 2 Slenderness Ratio 64.0% Post 9 Passed 2 x 4 DFL SS 2 Slenderness Ratio 64.0% Disclosure Use of the Boise Cascade Software is subject to the terms of the End User License Agreement(EULA).Completeness and accuracy of input must be reviewed and verified by a qualified engineer or other appropriate expert to assure its adequacy, prior to anyone relying on such output as evidence of suitability for a particular application. The output here is based on building code-accepted design properties and analysis methods. Installation of Boise Cascade engineered wood products must be in accordance with current Installation Guide and applicable building codes.To obtain Installation Guide or ask questions, please call (800)232-0788 before installation. BC CALL®,BC FRAMER®,AJSTM',ALLJOIST®,BC RIM BOARDN,BCI®,BOISE GLULAMTM',BC FloorValue®,VERSA-LAM®,VERSA-RIM PLUS®, VERSA-RIM®,VERSA-STRAND®,VERSA-STUD®are trademarks of Boise Cascade Wood Products L.L.C. °Pe <c- D PN O Fg ss/ot 92692PE �l OREGON e ✓��y 13,2o. %0� `FB f o w k0 EXPIRES:12/31/23 Page 1 of 15 ®Boise Cascade' Single 5-1/8" x 12" BOISE GLULAM®24F-V4/DF PASSED ENGINEERED WOOD PRODUCTS Beam 1 (Living Room)(Roof Drop Beam) BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. <1° 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 l l l 1 1 1 1 14, 1 1 ♦ ♦ 1 1 1 1 1 1 0 1 1 1 1 11 .1 1 1 1 1 1 1 ♦ 1 1 k / 15-oaoo B1 B2 Total Horizontal Product Length=15-07-00 Reaction Summary (Down / Uplift) (Ibs) Bearing Live Dead Snow Wind Roof Live B1, 3-1/2" 909/0 2390/0 2274/0 B2,3-1/2" 909/0 2390/0 2274/0 Load Summary Live Dead Snow Wind Roof Tributary Live Tag Description Load Type Ref. Start End Loc. 100% 90% 115% 160% 125% 0 Self-Weight Unf. Lin. (Ib/ft) L 00-00-00 15-07-00 Top 15 00-00-00 2 Unf.Area(Ib/ft2) L 00-00-00 15-07-00 Top 10 25 25 11-08-01 Controls Summary Value %Allowable Duration Case Location Pos. Moment 17533 ft-lbs 62.0% 115% 6 07-09-08 End Shear 3985 lbs 31.9% 115% 6 01-03-08 Total Load Deflection U334(0.543") 71.9% n\a 6 07-09-08 Live Load Deflection L/668(0.272") 53.9% n\a 12 07-09-08 Max Defl. 0.543" 54.3% n\a 6 07-09-08 Span/Depth 15.1 %Allow %Allow Bearing Supports Dim.(LxW) Value Support Member Material B1 Wall/Plate 3-1/2"x 5-1/8" 4777 lbs n\a 41.0% Unspecified B2 Column 3-1/2"x 5-1/8" 4777 lbs n\a 41.0% Unspecified Cautions For roof members with slope(1/4)/12 or less final design must ensure that ponding instability will not occur. For roof members with slope(1/2)/12 or less final design must account for Rain-on-Snow surcharge load. Notes Design meets User specified(L/240)Total load deflection criteria. Design meets User specified(U360)Live load deflection criteria. Design meets arbitrary(1")Maximum Total load deflection criteria. Design based on Dry Service Condition. BC CALC®analysis is based on IBC 2009. Calculations assume member is fully braced. Page 2 of 15 ®Boise Cascade Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF PASSED ENGINEERED WOOD PRODUCTS Beam 2 (Hall) (Roof Drop Beam) BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. ' �0 12 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 121 1 1 11 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 01 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1_. 06-06-00 B1 B2 Total Horizontal Product Length=07-01-00 Reaction Summary (Down / Uplift) (Ibs) Bearing Live Dead Snow Wind Roof Live B1,3-1/2" 413/0 1067/0 1033/0 B2, 3-1/2" 413/0 1067/0 1033/0 Load Summary Live Dead Snow Wind Roof Tributary Live Tag Description Load Type Ref. Start End Loc. 100% 90% 115% 160% 125% 0 Self-Weight Unf. Lin.(lb/ft) L 00-00-00 07-01-00 Top 9 00-00-00 2 Unf.Area(Ib/ft2) L 00-00-00 07-01-00 Top 10 25 25 11-08-01 Controls Summary Value %Allowable Duration Case Location Pos. Moment 3333 ft-lbs 30.2% 115% 6 03-06-08 End Shear 1595 lbs 20.4% 115% 6 00-11-00 Total Load Deflection U999(0.081") n\a n\a 6 03-06-08 Live Load Deflection U999(0.041") n\a n\a 12 03-06-08 Max Defl. 0.081" n\a n\a 6 03-06-08 Span/Depth 10.6 %Allow %Allow Bearing Supports Dim.(LxW) Value Support Member Material B1 Wall/Plate 3-1/2"x 5-1/8" 2152 lbs n\a 18.5% Unspecified B2 Column 3-1/2"x 5-1/8" 2152 lbs n\a 18.5% Unspecified Cautions _ For roof members with slope(1/4)/12 or less final design must ensure that ponding instability will not occur. For roof members with slope(1/2)/12 or less final design must account for Rain-on-Snow surcharge load. Notes Design meets User specified(L/240)Total load deflection criteria. Design meets User specified(U360)Live load deflection criteria. Design meets arbitrary(1")Maximum Total load deflection criteria. Design based on Dry Service Condition. BC CALC®analysis is based on IBC 2009. Calculations assume member is fully braced. Page 3 of 15 Boise Cascade' Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF PASSED ENGINEERED WOOD PRODUCTS Beam 3(Stairs) (Roof Drop Beam) BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. <10 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 121 1 1 1 1 1 1 1 1 1 1 1 _ l l 1 1 1 1 1 1" 1 1 ♦ 1 1 1 1 1 1 1 1 1 01 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 • i 03-00-00 B1 B2 Total Horizontal Product Length=03-07-00 Reaction Summary (Down /Uplift) (Ibs) Bearing Live Dead Snow Wind Roof Live B1,3-1/2" 209/0 540/0 523/0 B2,3-1/2" 209/0 540/0 523/0 Load Summary Live Dead Snow Wind Roof Tributary Live Tag Description Load Type Ref. Start End Loc. 100% 90% 115% 160% 125% 0 Self-Weight Unf. Lin.(lb/ft) L 00-00-00 03-07-00 Top 9 00-00-00 2 Unf.Area(Ib/ft2) L 00-00-00 03-07-00 Top 10 25 25 11-08-01 Controls Summary Value %Allowable Duration Case Location Pos. Moment 742 ft-lbs 6.7% 115% 6 01-09-08 End Shear 532 lbs 6.8% 115% 6 00-11-00 Total Load Deflection U999(0.004") n\a n\a 6 01-09-08 Live Load Deflection U999(0.002") n\a n\a 12 01-09-08 Max Defl. 0.004" n\a n\a 6 01-09-08 Span/Depth 5.0 %Allow %Allow Bearing Supports Dim.(LxW) Value Support Member Material B1 Wall/Plate 3-1/2"x 5-1/8" 1088 lbs n\a 9.3% Unspecified B2 Column 3-1/2"x 5-1/8" 1088 lbs n\a 9.3% Unspecified Cautions For roof members with slope(1/4)/12 or less final design must ensure that ponding instability will not occur. For roof members with slope(1/2)/12 or less final design must account for Rain-on-Snow surcharge load. Notes Design meets User specified(L/240)Total load deflection criteria. Design meets User specified(L/360)Live load deflection criteria. Design meets arbitrary(1")Maximum Total load deflection criteria. Design based on Dry Service Condition. BC CALC®analysis is based on IBC 2009. Calculations assume member is fully braced. Page 4 of 15 ®Boise - Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF PASSED ENGNEERED WOOD PRODUCTS Beam 4(Kitchen) (Roof Drop Beam) BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. <10 12 1 1 1 1 1 1 1 1 1 1 1 1 1 11 114 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4 1 1 1 _..1 4 1 4 4 104 1 4 1 1 4 1 4 4 1 4 1 1 1 1 1 ,. 14-04-00 61 B2 Total Horizontal Product Length=15-03-00 Reaction Summary (Down / Uplift) (Ibs) Bearing Live Dead Snow Wind Roof Live B1, 5-1/2" 763/0 834/0 B2, 5-1/2" 763/0 834/0 Load Summary Live Dead Snow Wind Roof Tributary Live Tag Description Load Type Ref. Start End Loc. 100% 90% 115% 160% 125% 0 Self-Weight Unf. Lin.(lb/ft) L 00-00-00 15-03-00 Top 9 00-00-00 1 Unf.Area(lb/ft2) L 00-00-00 15-03-00 Top 10 10 10-00-00 Controls Summary Value %Allowable Duration Case Location Pos. Moment 5470 ft-lbs 56.9% 100% 1 07-07-08 End Shear 1369 lbs 20.2% 100% 1 01-01-00 Total Load Deflection U273(0.635") 87.8% n\a 1 07-07-08 Live Load Deflection U572(0.303") 62.9% n\a 5 07-07-08 Max Defl. 0.635" 63.5% n\a 1 07-07-08 Span/Depth 23.1 %Allow %Allow Bearing Supports Dim.(LxW) Value Support Member Material B1 Wall/Plate 5-1/2"x 5-1/8" 1596 lbs n\a 8.7% Unspecified B2 Wall/Plate 5-1/2"x 5-1/8" 1596 lbs n\a 8.7% Unspecified Cautions _ For roof members with slope(1/4)/12 or less final design must ensure that ponding instability will not occur. For roof members with slope(1/2)/12 or less final design must account for Rain-on-Snow surcharge load. Notes Design meets User specified(U240)Total load deflection criteria. Design meets User specified(L/360)Live load deflection criteria. Design meets arbitrary(1")Maximum Total load deflection criteria. Design based on Dry Service Condition. BC CALC®analysis is based on IBC 2009. Calculations assume member is fully braced. Page 5 of 15 111►1Boisecascade Triple 2 x 4 DFL SS PASSED ENGINEERED WOOD PRODUCTS Post 1 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt. (Ibs) n\a n\a 909 2390 2274 4.5" Bracing Elevation Sheathing 3.5" Top 08-00-00 Base 00-00-00 E(Left-Right)=0.752" E(Front-Back)=0.585" 1 Controls Summary Value %Allowable Duration Case Axial Compression 4806 lbs 44.1% 115% 3 Axial Compression and Bending Front-Back n\a 42.7% 115% 3 08-p00-00 r--- '' Axial Compression and Bending Left-Right n\a 34.5% 115% 3 Slenderness Ratio 27.43 54.9% n\a 0 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 4-1/2"x 3-1/2" 4806 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. Page 6 of 15 ®� (liiilW Double 2 x 4 DFL SS PASSED ENGINEERED WOOD PRODUCTS Post 10 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% _1 Conc. Pt. (Ibs) n\a n\a 763 834 3" Bracing Elevation Sheathing Top 08-00-00 3.5" Base 00-00-00 Controls Summary Value %Allowable Duration Case E(Lett-Right)=0.501" E(Front-Back)=0.585" 1 Axial Compression 1616 lbs 39.7% 100% 1 Axial Compression and Bending Front-Back n\a 25.7% 100% 1 Axial Compression and Bending Left-Right n\a 25.0% 100% 1 Top0o-00 r • Slenderness Ratio 32.00 64.0% n\a 0 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 3"x 3-1/2" 1616 lbs n\a 100% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections,installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. Page 7 of 15 0 Boise r ill ... Single 5-1/8" x 5-1/2" BOISE GLULAM®24F-V4/DF PASSED ENGINEERED WOOD PRODUCTS Post 2 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt.(lbs) n\a n\a 1322 3547 3307 5.13" Bracing Elevation Sheathing a Top 08-00-00 5.5" Base 00-00-00 Controls Summa Value %Allowable Duration Case E(Left-Right)=0.856" I ry E(Front-Back)=0.919" i Axial Compression 7074 lbs 17.2% 115% 3 1 Axial Compression and Bending Front-Back n\a 13.4% 115% 3 Axial Compression and Bending Left-Right n\a 19.2% 115% 3 Top r--_ �� Slenderness Ratio 18.73 37.5% n\a 0 08-00-00 _� t Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 5-1/8"x 5-1/2" 7074 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). Design assumes zero camber in the member. BC Calc does not perform shear wall or connection design for in-plane load transfer. BC CALC®analysis is based on IBC 2009. - •,, Page 8 of 15 ' a Boise' Cascade* IIII C Quadruple 2 x 4 DFL SS PASSED ENGINEERED WOOD PRODUCTS Post 3 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt. (lbs) n\a n\a 3162 2620 3307 6" Bracing Elevation Sheathing a 3.5" Top 08-00-00 Base 00-00-00 E(Left-Right)=1.002" 1 E(Front-Back)=0.585" 1 Controls Summary % Top Value Allowable Duration Case Axial Compression 7510 lbs 51.6% 115% 3 08-00-00 '116111- Axial Compression and Bending Front-Back n\a 57.4% 115% 3 1 Axial Compression and Bending Left-Right n\a 42.3% 115% 3 s1 Slenderness Ratio 27.43 54.9% n\a 0 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 6"x 3-1/2" 7510 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. Page 9 of 15 0 Boise Cascade` N Quadruple 2 x 4 DFL SS PASSED] ENGINEEREDW000 PROCUCTS Post 4 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof , Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt.(Ibs) n\a n\a 2242 3777 3307 6" Bracing Elevation Sheathing 3.5" Top 08-00-00 Base 00-00-00 E(Left-Right)=1.002" E(Front-Back)=0.585" 1 1 Controls Summary Value %Allowable Duration Case Top Axial Compression 7977 lbs 54.8% 115% 3 08-00-00 ' Axial Compression and Bending Front-Back n\a 64.9% 115% 3 ig Axial Compression and Bending Left-Right n\a 46.9% 115% 3 �� Slenderness Ratio 27.43 54.9% n\a 0 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 6"x 3-1/2" 7977 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the projects design professional of record. BC CALC®analysis is based on IBC 2009. SV Page 10 of 15 4) oise Boise' III Single 5-1/8" x 5-1/2" BOISE GLULAM®24F-V4/DF PASSED • ENGINEERED WOOD PRODUCTS Post 5 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page. See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% ,1 Conc. Pt. (Ibs) n\a n\a 622 1607 1556 5.13" Bracing Elevation Sheathing l Top 08-00-00 11 5.5" Base 00-00-00 Controls Summa o E(Left-Right)=0.856" ry Value /o Allowable Duration Case E(Front-Back)=0.919" I Axial Compression 3295 lbs 8.0% 115% 3 1 Axial Compression and Bending Front-Back n\a 5.2% 115% 3 Axial Compression and Bending Left-Right n\a 7.5% 115% 3 08 00-0o r ,1116 Slenderness Ratio 18.73 37.5% n\a 0 „t Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 5-1/8"x 5-1/2" 3295 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). Design assumes zero camber in the member. BC Caic does not perform shear wall or connection design for in-plane load transfer. BC CALC®analysis is based on IBC 2009. L--- .v Page 11 of 15 ®Boise Cascade' llllll� Double 2 x 4 DFL SS PASSED1 ENGINEERED WOOD vaooua s Post 6 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt.(lbs) n\a n\a 209 540 523 3" Bracing Elevation Sheathing Top 08-00-00 3.5" Base 00-00-00 Controls SummaryValue %Allowable Duration Case E(Left-Right)=0.501" E(Front-Back)=0.585" Axial Compression 1108 lbs 26.9% 115% 3 1 Axial Compression and Bending Front-Back n\a 12.8% 115% 3 Axial Compression and Bending Left-Right n\a 12.0% 115% 3 08-p00-00 r ''v:� Slenderness Ratio 32.00 64.0% n\a 0 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 3"x 3-1/2" 1108 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. "J Page 12 of 15 0. Boise Triple 2 x 4 DFL SS PASSED ENGINEERED WOOD PRODUCTS Post 7 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% _1 Conc. Pt. (Ibs) n\a n\a 1542 1837 1556 4.5' Bracing Elevation Sheathing i Top 08-00-00 3.5" Base 00-00-00 E(Left-Right)=0.752" E(Front-Back)=0.585" 1 Controls Summary Value %Allowable Duration Case Axial Compression 4189 Ibs 38.4% 115% 3 Axial Compression and Bending Front-Back n\a 33.2% 115% 3 08-p00-00 r Axial Compression and Bending Left-Right n\a 27.3% 115% 3 Slenderness Ratio 27.43 54.9% n\a 0 ,%t Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 4-1/2"x 3-1/2" 4189 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. Page 13 of 15 Boise Cascade' Double 2 x 4 DFL SS PASSEDl ENGINEERED W000 PRODUCTS Post 8 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page.See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt.(Ibs) n\a n\a 1139 770 523 3•• Bracing Elevation Sheathing Top 08-00-00 3.5" Base 00-00-00 Controls SummaryValue %Allowable Duration Case E(Left-Right)=0.501" E(Front-Back)=0.585" Axial Compression 2036 lbs 49.5% 115% 3 1 Axial Compression and Bending Front-Back n\a 36.5% 115% 3 Axial Compression and Bending Left-Right n\a 35.9% 115% 3 Top00-00 r ,��•� Slenderness Ratio 32.00 64.0% n\a 0 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 3"x 3-1/2" 2036 lbs n\a 115% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. sJ Page 14 of 15 Cascade' a Boise. IIII Double 2 x 4 DFL SS PASSED ENGINEERED WOOD PRODUCTS Post 9 BC CALC®Member Report April 10,2023 22:03:33 Description: This report has a cover page. See the cover page(s)for project data and important information regarding this analysis and product installation. Load Summary Live Dead Snow Wind Roof Live Tag Description Load Type Start End 100% 90% 115% 160% 125% 1 Conc. Pt. (Ibs) n\a n\a 763 834 3" Bracing Elevation Sheathing I Top 08-00-00 3.5" Base 00-00-00 Controls Summary % E(Left-Right)=0.501" Value Allowable Duration Case E(Front-Back)=0.585" Axial Compression 1616 lbs 39.7% 100% 1 1 Axial Compression and Bending Front-Back n\a 25.7% 100% 1 Axial Compression and Bending Left-Right n\a 25.0% 100% 1 08 00-00 r ®'u Slenderness Ratio 32.00 64.0% n\a 0 ,1 Bearing Supports Dim.(LxW) Value %Allowable Duration Material Wall 3"x 3-1/2" 1616 lbs n\a 100% Unspecified Notes Allowable loads are based on a minimum eccentricity of 0.167 multiplied by the column thickness or width(worst case). BC Calc does not perform shear wall or connection design for in-plane load transfer. The analysis of solid sawn wood members is in accordance with the NDS and is limited to the output shown above.All other support and design for these products, including but not limited to notching, connections, installation,and engineer/architect certification is the responsibility of the project's design professional of record. BC CALC®analysis is based on IBC 2009. . Page 15 of 15 al Boise Cascade Single 5-1/8" x 12" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 1 (Living Room) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 180"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Factored Product Data E= 1.80 x 106 psi Shear= 10865 lbs Compression Perpendicular to Grain=650 psi. El= 1328.40 x 106 lb-in2 Moment=24600 ft-lbs Emin=0.93 X 106 psi Modification Factors Factor Moment Neg. Moment Shear End Reaction Int. Reaction Bearing Load Duration 115% 115% 115% Moisture Content 1.00 1.00 1.00 Lateral Stability 1.00 Unbraced Length 00-00-00 Repetitive Member Volume 1.00 Notch/Bevel 1.00 Maximum Values A 15-01-08 A Moment(ft-lbs) 0 17533 0 Shear(Ibs) -2301 4598 Shear Red.(Ibs) 613 613 Reaction(lbs) 4777 4777 Uplift(lbs) 0 0 Total Defl.(in) 0.543" Live Defl.(in) 0.272" Neg. Defl. (in) 0" Live Neg. Defl.(in) 0" Load cases Loadcase#0:(1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs --- Point Load Dead Load 00-00-00 ---- 3.43 lbs --- Point Load Dead Load 15-07-00 -- 66.87 lbs -- Point Load Dead Load 15-07-00 ---- 3.43 lbs --- Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft ---- . Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft ---- A 15-01-08 A Moment(ft-lbs) 0 8772 0 Shear(Ibs) -2301 2301 Shear Red. (lbs) 307 307 Reaction(Ibs) 2390 2390 Uplift(Ibs) 0 0 Total Defl.(in) 0.272" Neg. Defl. (in) 0" Loadcase#1:(1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 --- 26.75 lbs --- Point Load Dead Load 00-00-00 ---- 66.87 lbs ---- Point Load Dead Load 00-00-00 ---- 3.43 lbs --- Point Load Live Load 15-07-00 --- 26.75 lbs --- Page 1 of 38 ®E - Single 5-1/8" x 12" BOISE GLULAM®24F-V4/DF Beam 1 (Living Room) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. 1180"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 15-07-00 --- 66.87 lbs Point Load Dead Load 15-07-00 ---- 3.43 lbs ---- Uniform Linear Load Live Load 00-02-12 15-04-04 116.72 lb/ft ---- Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft ---- Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft ---- A• 15-01-08 A Moment(ft-lbs) 0 12109 0 Shear(Ibs) -3176 3176 Shear Red. (Ibs) 423 423 Reaction(Ibs) 3299 3299 Uplift(Ibs) 0 0 Total Defl.(in) 0.375" Neg. Defl. (in) 0" Loadcase#2: (1.00D+1.00LP_1) 1.00 Dead Load+ 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 66.87 lbs -- Point Load Dead Load 00-00-00 --- 3.43 lbs Point Load Dead Load 15-07-00 --- 66.87 lbs Point Load Dead Load 15-07-00 ---- 3.43 lbs --- Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft -- Uniform Linear Load Construction Load 00-03-08 02-09-00 118.77 lb/ft ---- A 15-01-08 A Moment(ft-lbs) 0 8961 0 Shear(lbs) -2568 2326 Shear Red. (Ibs) 426 307 Reaction(Ibs) 2657 2415 Uplift(Ibs) 0 0 Total Defl.(in) 0.279" Neg. Defl. (in) 0" Loadcase#3: (1.00D+1.00LP_2) 1.00 Dead Load+ 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs Point Load Dead Load 00-00-00 ---- 3.43 lbs - - Point Load Dead Load 15-07-00 --- 66.87 lbs Point Load Dead Load 15-07-00 ---- 3.43 lbs --- Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft --- ' Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft -- Uniform Linear Load Construction Load 06-06-12 09-00-04 118.77 Ib/ft --- A 15-01-08 A Moment(ft-lbs) 0 9787 0 Shear(Ibs) -2447 2447 Shear Red. (Ibs) 307 307 Reaction(Ibs) 2536 2536 Uplift(Ibs) 0 0 Total Defl. (in) 0.299" Neg. Defl. (in) 0" Loadcase#4: (1.00D+1.00LP_3) 1.00 Dead Load+ 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs Point Load Dead Load 00-00-00 -- 3.43 lbs -- Point Load Dead Load 15-07-00 ---- 66.87 lbs -- Page 2 of 38 0 Boise Cascade' IIII---- Single 5-1/8" x 12" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 1 (Living Room)(Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. 1180"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 15-07-00 -- 3.43 lbs -- Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft --- Uniform Linear Load Construction Load 12-10-00 15-03-08 118.77 lb/ft ---- A 15-01-08 A Moment(ft-lbs) 0 8961 0 . Shear(Ibs) -2326 2568 Shear Red. (Ibs) 307 426 Reaction(Ibs) 2415 2657 Uplift(Ibs) 0 0 Total Defl. (in) 0.279" Neg. Defl. (in) 0" Loadcase#5: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs --- Point Load Snow Load 00-00-00 --- 66.87 lbs -- Point Load Dead Load 00-00-00 -- 3.43 lbs --- Point Load Dead Load 15-07-00 ---- 66.87 lbs - Point Load Snow Load 15-07-00 --- 66.87 lbs --- Point Load Dead Load 15-07-00 - 3.43 lbs - Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft -- Uniform Linear Load Snow Load 00-02-12 15-04-04 291.80 lb/ft -- Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft --- A 15-01-08 A Moment(ft-lbs) 0 17116 0 Shear(lbs) -4489 4489 Shear Red. (Ibs) 599 599 Reaction(Ibs) 4664 4664 Uplift(Ibs) 0 0 Total Defl. (in) 0.531" Neg. Defl.(in) 0" Loadcase#6:(1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load on span#1 +0.75 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 -- 26.75 lbs --- Point Load Dead Load 00-00-00 ---- 66.87 lbs --- Point Load Snow Load 00-00-00 ---- 66.87 lbs --- Point Load Dead Load 00-00-00 -- 3.43 lbs ---- Point Load Live Load 15-07-00 --- 26.75 lbs ---- Point Load Dead Load 15-07-00 ---- 66.87 lbs ---- Point Load Snow Load 15-07-00 ---- 66.87 lbs --- Point Load Dead Load 15-07-00 --- 3.43 lbs -- Uniform Linear Load Live Load 00-02-12 15-04-04 116.72 lb/ft --- Uniform Linear Load Dead Load 00-02-12 15-04-04 291.80 lb/ft --- Uniform Linear Load Snow Load 00-02-12 15-04-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 15-04-04 14.95 lb/ft -- A 15-01-08 A Moment(ft-lbs) 0 17533 0 Shear(Ibs) -4598 4598 Shear Red. (lbs) 613 613 Reaction(Ibs) 4777 4777 Uplift(Ibs) 0 0 Total Defl. (in) 0.543" Neg. Defl. (in) 0" Page 3 of 38 • aSingle 5-1/8" x 12" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 1 (Living Room) (Roof Drop Beam) BC CALC®Engineering Report Dry I 1 span I No cant. I 180"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Loadcase#7: (1.00L) 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 26.75 lbs ---- .Point Load Live Load 15-07-00 --- 26.75 lbs -- Uniform Linear Load Live Load 00-02-12 15-04-04 116.72 lb/ft ---- A 15-01-08 A Live Defl. (in) 0.103" Live Neg. Defl. (in) 0" Loadcase#8: (1.00S) 1.00 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Snow Load 00-00-00 --- 66.87 lbs --- Point Load Snow Load 15-07-00 --- 66.87 lbs ---- Uniform Linear Load Snow Load 00-02-12 15-04-04 291.80 lb/ft -- A 15-01-08 A Live Defl.(in) 0.259" Live Neg. Defl. (in) 0" Loadcase#9:(1.00LP_1) 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 00-03-08 02-09-00 118.77 lb/ft -- A 15-01-08 A Live Defl. (in) 0.007" Live Neg. Deft (in) 0" Loadcase#10: (1.00LP_2) 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 06-06-12 09-00-04 118.77 lb/ft ---- A 15-01-08 A Live Defl. (in) 0.027" Live Neg. Defl. (in) 0" Loadcase#11: (1.00LP_3) 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 12-10-00 15-03-08 118.77 lb/ft -- A 15-01-08 A Live Defl.(in) 0.007" Live Neg. Defl. (in) 0" Loadcase#12: (0.755+0.75L) 0.75 Live Load on span#1 +0.75 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 26.75 lbs -- Point Load Snow Load 00-00-00 ---- 66.87 lbs --- Point Load Live Load 15-07-00 -- 26.75 lbs --- Page 4 of 38 *Boise Cascade' Single 5-1/8" x 12" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 1 (Living Room) (Roof Drop Beam) BC CALC®Engineering Report Dry I 1 span I No cant. I 180"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Snow Load 15-07-00 --- 66.87 lbs — Uniform Linear Load Live Load 00-02-12 15-04-04 116.72 lb/ft --- Uniform Linear Load Snow Load 00-02-12 15-04-04 291.80 lb/ft -- A 15-01-08 A Live Defl. (in) 0.272" Live Neg. Defl.(in) 0" Page 5 of 38 @Boise Cascade -.- -- Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 2(Hall) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 85"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Factored Product Data E= 1.80 x 106 psi Shear=6791 lbs Compression Perpendicular to Grain =650 psi El =324.32 x 106 lb-in2 Moment=9609 ft-lbs Emu"=0.93 x 106 psi • Modification Factors Factor Moment Neg. Moment Shear End Reaction Int. Reaction Bearing Load Duration 115% 115% 115% Moisture Content 1.00 1.00 1.00 Lateral Stability 1.00 Unbraced Length 00-00-00 Repetitive Member • Volume 1.00 Notch/Bevel 1.00 Maximum Values A 06-07-08 A Moment(ft-lbs) 0 3333 0 Shear(Ibs) -979 1974 Shear Red. (Ibs) 380 380 Reaction(lbs) 2152 2152 Uplift(Ibs) 0 0 Total Defl. (in) 0.081" Live Defl. (in) 0.041" Neg. Defl. (in) 0" Live Neg. Defl. (in) 0" Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 66.87 lbs ---- Point Load Dead Load 00-00-00 ---- 2.14 lbs --- Point Load Dead Load 07-01-00 --- 66.87 lbs Point Load Dead Load 07-01-00 ---- 2.14 lbs -- • Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft -- A 06-07-08 A Moment(ft-lbs) 0 1652 0 Shear(Ibs) -979 979 Shear Red. (Ibs) 188 188 Reaction(lbs) 1067 1067 Uplift(Ibs) 0 0 Total Defl.(in) 0.04" Neg. Defl. (in) 0" Loadcase#1:(1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 --- 26.75 lbs Point Load Dead Load 00-00-00 --- 66.87 lbs ---- Point Load Dead Load 00-00-00 --- 2.14 lbs ---- Point Load Live Load 07-01-00 --- 26.75 lbs -- Page 6 of 38 ®Boise - Single 5-1/8" x 7-1/2" BOISE GLULAM® 24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 2(Hall) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 85"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 07-01-00 --- 66.87 lbs - Point Load Dead Load 07-01-00 --- 2.14 lbs ---- Uniform Linear Load Live Load 00-02-12 06-10-04 116.72 lb/ft --- Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft -- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft ---- A 06-07-08 A . Moment(ft-lbs) 0 2293 0 Shear(Ibs) -1358 1358 Shear Red.(Ibs) 261 261 Reaction(lbs) 1480 1480 Uplift(Ibs) 0 0 Total Defl. (in) 0.056" Neg. Defl. (in) 0" Loadcase#2:(1.00D+1.00LP_1) 1.00 Dead Load+ 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs ---- Point Load Dead Load 00-00-00 -- 2.14 lbs --- Point Load Dead Load 07-01-00 ---- 66.87 lbs -- Point Load Dead Load 07-01-00 --- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft ---- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft -- Uniform Linear Load Construction Load 00-03-08 02-09-00 118.77 lb/ft -- A 06-07-08 A Moment(ft-lbs) 0 1846 0 Shear(Ibs) -1214 1036 Shear Red. (Ibs) 262 188 Reaction(Ibs) 1302 1124 Uplift(Ibs) 0 0 Total Defl.(in) 0.045" Neg. Defl.(in) 0" Loadcase#3:(1.00D+1.00LP_2) 1.00 Dead Load+ 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs --- Point Load Dead Load 00-00-00 --- 2.14 lbs --- . Point Load Dead Load 07-01-00 ---- 66.87 lbs -- Point Load Dead Load 07-01-00 --- 2.14 lbs ---- Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft ---- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft -- Uniform Linear Load Construction Load 02-03-12 04-09-04 118.77 lb/ft --- A 06-07-08 A Moment(ft-lbs) 0 2046 0 Shear(lbs) -1125 1125 Shear Red. (Ibs) 188 188 Reaction(Ibs) 1213 1213 Uplift(Ibs) 0 0 Total Defl. (in) 0.049" Neg. Defl.(in) 0" Loadcase#4: (1.00D+1.00LP_3) 1.00 Dead Load+ 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs --- Point Load Dead Load 00-00-00 --- 2.14 lbs --- Point Load Dead Load 07-01-00 ---- 66.87 lbs -- Page 7 of 38 ®aasec�de Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 2(Hall) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 85"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 07-01-00 ---- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft ---- Uniform Linear Load Construction Load 04-04-00 06-09-08 118.77 lb/ft --- A 06-07-08 A Moment(ft-lbs) 0 1847 0 Shear(Ibs) -1036 1214 Shear Red. (lbs) 188 262 Reaction(Ibs) 1124 1302 Uplift(Ibs) 0 0 Total Defl. (in) 0.045" Neg. Defl. (in) 0" Loadcase#5: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs ---- Point Load Snow Load 00-00-00 ---- 66.87 lbs --- Point Load Dead Load 00-00-00 --- 2.14 lbs ---- Point Load Dead Load 07-01-00 --- 66.87 lbs ---- Point Load Snow Load 07-01-00 ---- 66.87 lbs -- Point Load Dead Load 07-01-00 --- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft --- Uniform Linear Load Snow Load 00-02-12 06-10-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft --- A 06-07-08 A Moment(ft-lbs) 0 3253 0 Shear(Ibs) -1927 1927 Shear Red.(Ibs) 371 371 Reaction(Ibs) 2100 2100 Uplift(Ibs) 0 0 Total Defl. (in) 0.079" Neg. Defl. (in) 0" Loadcase#6: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load on span#1 +0.75 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value - Point Load Live Load 00-00-00 --- 26.75 lbs --- Point Load Dead Load 00-00-00 --- 66.87 lbs --- Point Load Snow Load 00-00-00 ---- 66.87 lbs -- Point Load Dead Load 00-00-00 --- 2.14 lbs --- Point Load Live Load 07-01-00 -- 26.75 lbs -- Point Load Dead Load 07-01-00 ---- 66.87 lbs --- Point Load Snow Load 07-01-00 --- 66.87 lbs ---- Point Load Dead Load 07-01-00 --- 2.14 lbs ---- Uniform Linear Load Live Load 00-02-12 06-10-04 116.72 lb/ft --- Uniform Linear Load Dead Load 00-02-12 06-10-04 291.80 lb/ft -- Uniform Linear Load Snow Load 00-02-12 06-10-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 06-10-04 9.34 lb/ft --- A 06-07-08 A Moment(ft-lbs) 0 3333 0 Shear(Ibs) -1974 1974 Shear Red. (Ibs) 380 380 Reaction(Ibs) 2152 2152 Uplift(Ibs) 0 0 Total Defl. (in) 0.081" Neg. Defl. (in) 0" Page 8 of 38 ® - Single 5-1/8" x 7-1/2" BOISE GLULAM® 24F-V4/DF . ENGINEERED W000 PRODUCTS Beam 2(Hall)(Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 85"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Loadcase#7: (1.00L) 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 -- 26.75 lbs -- Point Load Live Load 07-01-00 --- 26.75 lbs -- . Uniform Linear Load Live Load 00-02-12 06-10-04 116.72 lb/ft ---- A 06-07-08 A Live Defl. (in) 0.016" Live Neg. Defl. (in) 0" Loadcase#8: (1.00S) 1.00 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Snow Load 00-00-00 --- 66.87 lbs ---- Point Load Snow Load 07-01-00 -- 66.87 lbs -- Uniform Linear Load Snow Load 00-02-12 06-10-04 291.80 lb/ft -- A 06-07-08 A Live Defl. (in) 0.039" Live Neg. Defl. (in) 0" Loadcase#9:(1.00LP_1) 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 00-03-08 02-09-00 118.77 lb/ft -- A 06-07-08 A Live Defl. (in) 0.005" Live Neg. Defl.(in) 0" Loadcase#10:(1.00LP_2) 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 02-03-12 04-09-04 118.77 lb/ft -- A 06-07-08 A Live Defl.(in) 0.009" Live Neg. Defl. (in) 0" Loadcase#11: (1.00LP_3) 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 04-04-00 06-09-08 118.77 lb/ft -- A 06-07-08 A Live Defl.(in) 0.005" Live Neg. Defl.(in) 0" Loadcase#12: (0.75S+0.75L) 0.75 Live Load on span#1 +0.75 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 26.75 lbs --- Point Load Snow Load 00-00-00 ---- 66.87 lbs ---- Point Load Live Load 07-01-00 --- 26.75 lbs -- Page 9 of 38 • . ®BdseCascade — Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 2(Hall)(Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 85"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Snow Load 07-01-00 -- 66.87 lbs -- Uniform Linear Load Live Load 00-02-12 06-10-04 116.72 lb/ft --- Uniform Linear Load Snow Load 00-02-12 06-10-04 291.80 lb/ft -- A 06-07-08 A Live Defl.(in) 0.041" . Live Neg. Defl. (in) 0" Page 10 of 38 ®Wail cascade' Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED W000 PRODUCTS Beam 3(Stairs)(Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 43"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Factored Product Data E= 1.80 x 106 psi Shear=6791 lbs Compression Perpendicular to Grain=650 psi El=324.32 x 106 lb-in2 Moment=9609 ft-lbs Emin=0.93 X 106 psi Modification Factors Factor Moment Neg. Moment Shear End Reaction Int. Reaction Bearing Load Duration 115% 115% 115% Moisture Content 1.00 1.00 1.00 Lateral Stability 1.00 Unbraced Length 00-00-00 Repetitive Member Volume 1.00 Notch/Bevel 1.00 Maximum Values A 03-01-08 A Moment(ft-lbs) 0 742 0 Shear(Ibs) -452 911 Shear Red. (Ibs) 380 380 Reaction(Ibs) 1088 1088 Uplift(lbs) 0 0 Total Defl. (in) 0.004" Live Defl. (in) 0.002" Neg. Defl. (in) 0" Live Neg. Defl. (in) 0" Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs -- Point Load Dead Load 00-00-00 -- 2.14 lbs ---- Point Load Dead Load 03-07-00 ---- 66.87 lbs ---- Point Load Dead Load 03-07-00 --- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft --- . Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft -- A 03-01-08 A Moment(ft-lbs) 0 368 0 Shear(Ibs) -452 452 Shear Red. (Ibs) 188 188 Reaction(Ibs) 540 540 Uplift(Ibs) 0 0 Total Defl. (in) 0.002" Neg. Defl.(in) 0" Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 — 26.75 lbs -- Point Load Dead Load 00-00-00 --- 66.87 lbs ---- Point Load Dead Load 00-00-00 -- 2.14 lbs --- Point Load Live Load 03-07-00 --- 26.75 lbs Page 11 of 38 • . aBo1secascade Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 3 (Stairs) (Roof Drop Beam) BC CALC®Engineering Report Dry l 1 span 1 No cant. 143"OCS 1 Non-Repetitive 1 0/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 03-07-00 ---- 66.87 Ibs --- Point Load Dead Load 03-07-00 --- 2.14 lbs ---- Uniform Linear Load Live Load 00-02-12 03-04-04 116.72 lb/ft --- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft ---- Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft --- A• 03-01-08 A Moment(ft-lbs) 0 510 0 Shear(Ibs) -627 627 Shear Red. (Ibs) 261 261 Reaction(Ibs) 749 749 Uplift(Ibs) 0 0 Total Defl. (in) 0.003" Neg. Defl.(in) 0" Loadcase#2: (1.00D+1.00LP_1) 1.00 Dead Load+ 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs ---- Point Load Dead Load 00-00-00 --- 2.14 lbs --- Point Load Dead Load 03-07-00 --- 66.87 lbs -- Point Load Dead Load 03-07-00 ---- 2.14 lbs ---- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft ---- Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft ---- Uniform Linear Load Construction Load 00-03-08 02-09-00 118.77 lb/ft -- A 03-01-08 A Moment(ft-lbs) 0 502 0 Shear(Ibs) -623 573 Shear Red.(Ibs) 262 188 Reaction(Ibs) 711 660 Uplift(Ibs) 0 0 Total Defl. (in) 0.003" Neg. Deft (in) 0" Loadcase#3: (1.00D+1.00LP_2) 1.00 Dead Load+ 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 66.87 lbs --- _ Point Load Dead Load 00-00-00 --- 2.14 lbs -- Point Load Dead Load 03-07-00 --- 66.87 lbs ---- Point Load Dead Load 03-07-00 ---- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft --- • Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft --- Uniform Linear Load Construction Load 00-06-12 03-00-04 118.77 lb/ft ---- A 03-01-08 A Moment(ft-lbs) 0 506 0 Shear(lbs) -598 598 Shear Red. (Ibs) 188 188 Reaction(Ibs) 686 686 Uplift(Ibs) 0 0 Total Defl. (in) 0.003" Neg. Defl. (in) 0" Loadcase#4:(1.00D+1.00LP_3) 1.00 Dead Load+ 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs --- Point Load Dead Load 00-00-00 --- 2.14 lbs --- Point Load Dead Load 03-07-00 --- 66.87 lbs --- Page 12 of 38 0 Boise c - Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 3(Stairs)(Roof Drop Beam) BC CALC®Engineering Report Dry I 1 span I No cant. I 43"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 03-07-00 --- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft -- Uniform Linear Load Construction Load 00-10-00 03-03-08 118.77 lb/ft --- . A 03-01-08 A Moment(ft-lbs) 0 502 0 Shear(Ibs) -573 623 Shear Red. (Ibs) 188 262 Reaction(lbs) 661 711 Uplift(Ibs) 0 0 Total Defl. (in) 0.003" Neg. Defl. (in) 0" Loadcase#5: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 66.87 lbs -- Point Load Snow Load 00-00-00 --- 66.87 lbs -- Point Load Dead Load 00-00-00 --- 2.14 lbs --- Point Load Dead Load 03-07-00 --- 66.87 lbs --- Point Load Snow Load 03-07-00 --- 66.87 lbs --- Point Load Dead Load 03-07-00 --- 2.14 lbs --- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft --- Uniform Linear Load Snow Load 00-02-12 03-04-04 291.80 lb/ft -- Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft --- A 03-01-08 A Moment(ft-lbs) 0 724 0 Shear(Ibs) -889 889 Shear Red.(Ibs) 371 371 Reaction(lbs) 1062 1062 Uplift(Ibs) 0 0 Total Defl. (in) 0.004" Neg. Defl. (in) 0" Loadcase#6:(1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load on span#1 +0.75 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 --- 26.75 lbs -- _ Point Load Dead Load 00-00-00 -- 66.87 lbs ---- Point Load Snow Load 00-00-00 -- 66.87 lbs -- Point Load Dead Load 00-00-00 ---- 2.14 lbs -- Point Load Live Load 03-07-00 --- 26.75 lbs -- Point Load Dead Load 03-07-00 --- 66.87 lbs ---- Point Load Snow Load 03-07-00 --- 66.87 lbs --- Point Load Dead Load 03-07-00 --- 2.14 lbs --- Uniform Linear Load Live Load 00-02-12 03-04-04 116.72 lb/ft --- Uniform Linear Load Dead Load 00-02-12 03-04-04 291.80 lb/ft ---- Uniform Linear Load Snow Load 00-02-12 03-04-04 291.80 lb/ft --- Uniform Linear Load Dead Load 00-02-12 03-04-04 9.34 lb/ft -- A 03-01-08 A Moment(ft-lbs) 0 742 0 Shear(Ibs) -911 911 Shear Red. (Ibs) 380 380 Reaction(Ibs) 1088 1088 Uplift(Ibs) 0 0 Total Defl.(in) 0.004" Neg. Defl.(in) 0" Page 13 of 38 • ® LW- Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PND W CTS Beam 3(Stairs) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 43"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Loadcase#7:(1.00L) 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 26.75 lbs ---- .Point Load Live Load 03-07-00 --- 26.75 lbs --- Uniform Linear Load Live Load 00-02-12 03-04-04 116.72 lb/ft ---- A 03-01-08 A Live Deft. (in) 0.001" Live Neg. Defl. (in) 0" Loadcase#8:(1.00S) 1.00 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Snow Load 00-00-00 --- 66.87 lbs --- Point Load Snow Load 03-07-00 --- 66.87 lbs --- Uniform Linear Load Snow Load 00-02-12 03-04-04 291.80 lb/ft ---- A 03-01-08 A Live Defl. (in) 0.002" Live Neg. Defl.(in) 0" Loadcase#9: (1.00LP_1) 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 00-03-08 02-09-00 118.77 lb/ft --- A 03-01-08 A Live Defl. (in) 0.001" Live Neg. Defl. (in) 0" Loadcase#10: (1.00LP_2) 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 00-06-12 03-00-04 118.77 lb/ft ---- A 03-01-08 A Live Defl. (in) 0.001" Live Neg. Defl. (in) 0" Loadcase#11: (1.00LP_3) 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 00-10-00 03-03-08 118.77 lb/ft --- A 03-01-08 A Live Defl. (in) 0.001" Live Neg. Defl. (in) 0" Loadcase#12: (0.75S+0.75L) 0.75 Live Load on span#1 +0.75 Snow Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 26.75 lbs --- Point Load Snow Load 00-00-00 ---- 66.87 lbs ---- Point Load Live Load 03-07-00 -- 26.75 lbs -- Page 14 of 38 se..... Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS • Beam 3(Stairs) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 43"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Snow Load 03-07-00 -- 66.87 lbs Uniform Linear Load Live Load 00-02-12 03-04-04 116.72 lb/ft -- Uniform Linear Load Snow Load 00-02-12 03-04-04 291.80 lb/ft -- A 03-01-08 A Live Defl. (in) 0.002" Live Neg. Defl. (in) 0" Page 15 of 38 ®eases Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 4(Kitchen) (Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. 1172"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Factored Product Data E= 1.80 x 106 psi Shear=6791 lbs Compression Perpendicular to Grain =650 psi El=324.32 x 106 lb-in2 Moment=9609 ft-lbs Em;,,=0.93 X 106 psi Modification Factors Factor Moment Neg. Moment Shear End Reaction Int. Reaction Bearing Load Duration 100% 100% 100% Moisture Content 1.00 1.00 1.00 Lateral Stability 1.00 Unbraced Length 00-00-00 Repetitive Member Volume 1.00 Notch/Bevel 1.00 Maximum Values A 14-05-08 A Moment(ft-lbs) 0 5470 0 Shear(Ibs) -784 1500 Shear Red. (Ibs) 143 143 Reaction(Ibs) 1596 1596 Uplift(Ibs) 0 0 Total Defl. (in) 0.635" Live Defl.(in) 0.303" Neg. Defl. (in) 0" Live Neg. Defl. (in) 0" Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 39.58 lbs ---- Point Load Dead Load 00-00-00 ---- 3.70 lbs ---- - Point Load Dead Load 15-03-00 -- 39.58 lbs -- Point Load Dead Load 15-03-00 ---- 3.70 lbs ---- Uniform Linear Load Dead Load 00-04-12 14-10-04 100.00 lb/ft --- Uniform Linear Load Dead Load 00-04-12 14-10-04 9.34 lb/ft ---- A 14-05-08 A Moment(ft-lbs) 0 2857 0 Shear(Ibs) -784 784 Shear Red. (Ibs) 68 68 Reaction(Ibs) 834 834 Uplift(Ibs) 0 0 Total Defl. (in) 0.331" Neg. Defl. (in) 0" Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 39.58 lbs ---- Point Load Dead Load 00-00-00 -- 39.58 lbs --- Point Load Dead Load 00-00-00 ---- 3.70 lbs ---- Point Load Live Load 15-03-00 --- 39.58 lbs ---- Page 16 of 38 ® Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PR000CTS Beam 4(Kitchen)(Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. 1172"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 15-03-00 --- 39.58 lbs Point Load Dead Load 15-03-00 --- 3.70 lbs --- Uniform Linear Load Live Load 00-04-12 14-10-04 100.00 lb/ft --- Uniform Linear Load Dead Load 00-04-12 14-10-04 100.00 lb/ft --- , Uniform Linear Load Dead Load 00-04-12 14-10-04 9.34 lb/ft --- A 14-05-08 A . Moment(ft-lbs) 0 5470 0 Shear(Ibs) -1500 1500 Shear Red. (lbs) 131 131 Reaction(lbs) 1596 1596 Uplift(lbs) 0 0 Total Defl. (in) 0.635" Neg. Defl. (in) 0" Loadcase#2: (1.00D+1.00LP_1) 1.00 Dead Load+ 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 39.58 lbs -- Point Load Dead Load 00-00-00 --- 3.70 lbs - Point Load Dead Load 15-03-00 --- 39.58 lbs ---- Point Load Dead Load 15-03-00 ---- 3.70 lbs --- Uniform Linear Load Dead Load 00-04-12 14-10-04 100.00 lb/ft ---- Uniform Linear Load Dead Load 00-04-12 14-10-04 9.34 lb/ft -- Uniform Linear Load Construction Load 00-05-08 02-11-00 118.77 lb/ft --- A 14-05-08 A Moment(ft-lbs) 0 3049 0 Shear(Ibs) -1050 810 Shear Red. (Ibs) 143 68 Reaction(Ibs) 1100 860 Uplift(Ibs) 0 0 Total Defl.(in) 0.357" Neg. Defl.(in) 0" Loadcase#3:(1.00D+1.00LP_2) 1.00 Dead Load+ 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 39.58 lbs -- Point Load Dead Load 00-00-00 -- 3.70 lbs --- _ Point Load Dead Load 15-03-00 ---- 39.58 lbs ---- _ Point Load Dead Load 15-03-00 --- 3.70 lbs -- Uniform Linear Load Dead Load 00-04-12 14-10-04 100.00 lb/ft --- Uniform Linear Load Dead Load 00-04-12 14-10-04 9.34 lb/ft --- Uniform Linear Load Construction Load 06-04-12 08-10-04 118.77 lb/ft --- A 14-05-08 A Moment(ft-lbs) 0 3824 0 Shear(lbs) -930 930 Shear Red.(Ibs) 68 68 Reaction(Ibs) 980 980 Uplift(Ibs) 0 0 Total Defl. (in) 0.428" Neg. Defl. (in) 0" Loadcase#4: (1.00D+1.00LP_3) 1.00 Dead Load+ 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 39.58 lbs -- Point Load Dead Load 00-00-00 --- 3.70 lbs ---- Point Load Dead Load 15-03-00 --- 39.58 lbs --- Page 17 of 38 • a Boise Cascade" Ili—W.—• Single 5-1/8" x 7-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Beam 4(Kitchen)(Roof Drop Beam) BC CALC®Engineering Report Dry 11 span I No cant. I 172"OCS I Non-Repetitive 10/12 April 10,2023 22:05:12 Build 16959 Point Load Dead Load 15-03-00 -- 3.70 lbs -- Uniform Linear Load Dead Load 00-04-12 14-10-04 100.00 lb/ft --- Uniform Linear Load Dead Load 00-04-12 14-10-04 9.34 lb/ft — Uniform Linear Load Construction Load 12-04-00 14-09-08 118.77 lb/ft ---- A 14-05-08 A . Moment(ft-lbs) 0 3049 0 Shear(Ibs) -810 1050 Shear Red. (Ibs) 68 143 Reaction(Ibs) 860 1100 Uplift(lbs) 0 0 Total Deft (in) 0.357" Neg. Defl. (in) 0" Loadcase#5: (1.00L) 1.00 Live Load on span#1 Load Type Component Start Pos End Pos Start Value End Value Point Load Live Load 00-00-00 ---- 39.58 lbs ---- Point Load Live Load 15-03-00 --- 39.58 lbs ---- Uniform Linear Load Live Load 00-04-12 14-10-04 100.00 lb/ft --- A 14-05-08 A Live Defl. (in) 0.303" Live Neg. Defl. (in) 0" Loadcase#6:(1.00LP_1) 1.00 Live Point Load on left side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 00-05-08 02-11-00 118.77 lb/ft ---- A 14-05-08 A Live Defl. (in) 0.026" Live Neg. Defl.(in) 0" Loadcase#7:(1.00LP_2) 1.00 Live Point Load at center of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 06-04-12 08-10-04 118.77 lb/ft --- A 14-05-08 A Live Defl. (in) 0.097" - Live Neg. Defl. (in) 0" Loadcase#8: (1.00LP_3) 1.00 Live Point Load on right side of span#1 Load Type Component Start Pos End Pos Start Value End Value Uniform Linear Load Construction Load 12-04-00 14-09-08 118.77 lb/ft ---- A 14-05-08 A Live Defl. (in) 0.026" Live Neg. Defl. (in) 0" Page 18 of 38 ® - Triple 2 x 4 DFL SS • ENGINEERED WOOD PRODUCTS Post 1 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.75" Iex=08-00-00 Kf=0.75 Slenderness Ratio x=21.33 c=0.80 _ Eccentricity y=0.58" ley=08-00-00 K.= 1.00 Slenderness Ratio y=27.43 Factored Product Data Ex= 1.90 x 106 psi Ey= 1.90 x 106 psi lx=5.36 in4 FDEX= 1246.95 psi FbE=9040.17 psi Eminx=0.69 x 106 psi Eminy=0.69 X 106 psi ly=0.98 in4 FDEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.38 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(lbs) 4806 Compression(psi) Compression and Bending(%) 42.7 34.5 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 28.88 lbs -- _ Point Load Dead Load 00-00-00 -- 2390.00 lbs --- _ Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction (Ibs) 2419 Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 28.88 lbs -- Point Load Live Load 00-00-00 --- 909.00 lbs ---- Point Load Dead Load 00-00-00 --- 2390.00 lbs --- Page 19 of 38 ®Boisecascade' Triple 2 x 4 DFL SS • ENGINEERED W000 PRODUCTS Post 1 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(lbs) 3328 Compression(psi) Loadcase#2:(1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 28.88 lbs Point Load Dead Load 00-00-00 --- 2390.00 lbs -- Point Load Snow Load 00-00-00 -- 2274.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 4693 Compression (psi) Loadcase#3: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 28.88 lbs --- Point Load Live Load 00-00-00 --- 909.00 lbs --- Point Load Dead Load 00-00-00 --- 2390.00 lbs --- Point Load Snow Load 00-00-00 --- 2274.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl. (in) Reaction(Ibs) 4806 Compression (psi) Page 20 of 38 ®Boisecascadll Double 2 x 4 DFL SS • ENGINEERED WOOD PRODUCTS Post 10 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.5" lex=08-00-00 Kf=0.75 Slenderness Ratio x=32.00 c=0.80 Eccentricity y=0.58" ley=08-00-00 K8= 1.00 Slenderness Ratio y=27.43 Factored Product Data • EX= 1.90 x 106 psi Ey= 1.90 x 106 psi Ix=5.36 in4 FcEx=554.20 psi FbE=6026.78 psi Eminx=0.69 x 106 psi Eminy=0.69 X 106 psi ly=0.98 in4 FcEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 100% 100% Moisture Content 1.00 Column Stability 0.22 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl. (in) Reaction(Ibs) 1616 Compression(psi) Compression and Bending(%) 25.7 25 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 19.25 lbs Point Load Dead Load 00-00-00 -- 834.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(lbs) 853 Compression(psi) Loadcase#1:(1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 19.25 lbs -- Point Load Live Load 00-00-00 --- 763.00 lbs --- Point Load Dead Load 00-00-00 --- 834.00 lbs ---- Page 21 of 38 • ®e�Cascade Double 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 10 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 1616 Compression(psi) Page 22 of 38 ®BoseCascader Single 5-1/8" x 5-1/2" BOISE GLULAM®24F-V4/DF . ENGINEERED WOOD PRODUCTS Post 2 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.86" le:=08-00-00 Kf= 1.00 Slenderness Ratio x= 18.73 c=0.90 Eccentricity y=0.92" ley=08-00-00 Ke= 1.00 Slenderness Ratio y= 17.45 Factored Product Data • EX= 1.80 x 106 psi Ey= 1.60 x 106 psi IX=71.06 in4 Fcex= 1943.01 psi FbE=26892.32 psi Eminx=0.93 x 106 psi Eminy=0.83 x 106 psi ly=61.70 in4 FDEy=2517.47 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.85 Lateral Stability Repetitive Member Volume Maximum Values Front-Back Left-Right Axial Bending (ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(lbs) 7074 Compression(psi) Compression and Bending (%) 13.4 19.2 Load cases Loadcase#0:(1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 54.81 lbs --- Point Load Dead Load 00-00-00 -- 3547.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 3602 Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 54.81 lbs --- Point Load Live Load 00-00-00 -- 1322.00 lbs --- Point Load Dead Load 00-00-00 --- 3547.00 lbs --- Page 23 of 38 . ®BoseCascadePSingle 5-1/8" x 5-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCE Post 2 BC CALC®Engineering Report Dry J 08-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-Ibs) • Shear(Ibs) - Total Defl. (in) Reaction(Ibs) 4924 . Compression(psi) Loadcase#2:(1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 54.81 lbs ---- Point Load Dead Load 00-00-00 -- 3547.00 lbs -- Point Load Snow Load 00-00-00 -- 3307.00 lbs ---- Front-Back Left-Right Axial Bending(ft-Ibs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 6909 Compression(psi) Loadcase#3:(1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 54.81 lbs --- Point Load Live Load 00-00-00 ---- 1322.00 lbs --- Point Load Dead Load 00-00-00 --- 3547.00 lbs ---- Point Load Snow Load 00-00-00 ---- 3307.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction (Ibs) 7074 Compression(psi) Page 24 of 38 ®Boise Cascade' Quadruple 2 x 4 DFL SS • ENGIN...4 WOOD PRODUCTS Post 3 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x= 1" lex=08-00-00 Kf=0.75 Slenderness Ratio x= 16.00 c=0.80 Eccentricity y=0.58" ley=08-00-00 KB= 1.00 Slenderness Ratio y=27.43 • Factored Product Data Ex= 1.90 x 106 psi Ey= 1.90 x 106 psi lx=5.36 in4 FcEx=2216.80 psi FbE= 12053.56 psi Eminx=0.69 x 106 psi Eminy=0.69 x 106 psi ly=0.98 in4 FcEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.38 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 7510 Compression(psi) Compression and Bending(%) 57.4 42.3 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 38.50 lbs --- Point Load Dead Load 00-00-00 ---- 2620.00 lbs ---- Front-Back Left-Right Axial • Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 2659 Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 38.50 lbs ---- Point Load Live Load 00-00-00 -- 3162.00 lbs ---- Point Load Dead Load 00-00-00 -- 2620.00 lbs --- Page 25 of 38 • ® - Quadruple 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 3 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) - Shear(Ibs) - Total Defl. (in) Reaction(Ibs) 5821 Compression(psi) Loadcase#2:(1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 38.50 lbs --- Point Load Dead Load 00-00-00 --- 2620.00 lbs --- Point Load Snow Load 00-00-00 --- 3307.00 lbs -- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 5966 Compression(psi) Loadcase#3: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 38.50 lbs -- Point Load Live Load 00-00-00 --- 3162.00 lbs -- Point Load Dead Load 00-00-00 --- 2620.00 lbs ---- Point Load Snow Load 00-00-00 --- 3307.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 7510 Compression(psi) Page 26 of 38 aBoise Cascade' Quadruple 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 4 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x= 1" lex=08-00-00 Kr=0.75 Slenderness Ratio x= 16.00 c=0.80 Eccentricity y=0.58" ley=08-00-00 Ke= 1.00 Slenderness Ratio y=27.43 . Factored Product Data Ex= 1.90 x 106 psi Ey= 1.90 x 106 psi lx=5.36 in4 FbEx=2216.80 psi FbE= 12053.56 psi Eminx=0.69 X 106 psi Eminy=0.69 x 106 psi ly=0.98 in4 FCEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.38 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 7977 Compression(psi) Compression and Bending(%) 64.9 46.9 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 — 38.50 lbs — _ Point Load Dead Load 00-00-00 --- 3777.00 lbs -- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) 3816 Reaction(Ibs) Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 38.50 lbs --- Point Load Live Load 00-00-00 ---- 2242.00 lbs -- Point Load Dead Load 00-00-00 --- 3777.00 lbs --- Page 27 of 38 Quadruple 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 4 BC CALL®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) • Shear(Ibs) Total Defl. (in) Reaction (lbs) 6058 Compression(psi) Loadcase#2:(1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 38.50 lbs ---- Point Load Dead Load 00-00-00 ---- 3777.00 lbs --- Point Load Snow Load 00-00-00 ---- 3307.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 7123 Compression(psi) Loadcase#3: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 38.50 lbs ---- Point Load Live Load 00-00-00 --- 2242.00 lbs -- Point Load Dead Load 00-00-00 ---- 3777.00 lbs --- Point Load Snow Load 00-00-00 ---- 3307.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl.(in) Reaction (Ibs) 7977 Compression (psi) Page 28 of 38 l®edsecascada Single 5-1/8" x 5-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Post 5 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.86" lex=08-00-00 Kf= 1.00 Slenderness Ratio x= 18.73 c=0.90 Eccentricity y=0.92" ley=08-00-00 Ke= 1.00 Slenderness Ratio y= 17.45 Factored Product Data EX= 1.80 x 106 psi Ey= 1.60 x 106 psi IX=71.06 in4 FLEX= 1943.01 psi FbE=26892.32 psi Eminx=0.93 X 106 psi Eminy=0.83 x 106 psi ly=61.70 in4 FDEy=2517.47 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.85 Lateral Stability Repetitive Member Volume Maximum Values Front-Back Left-Right Axial Bending (ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 3295 Compression(psi) Compression and Bending (%) 5.2 7.5 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 54.81 lbs Point Load Dead Load 00-00-00 ---- 1607.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(lbs) 1662 Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 54.81 lbs --- Point Load Live Load 00-00-00 ---- 622.00 lbs --- Point Load Dead Load 00-00-00 ---- 1607.00 lbs --- Page 29 of 38 ® III Single 5-1/8" x 5-1/2" BOISE GLULAM®24F-V4/DF ENGINEERED WOOD PRODUCTS Post 5 BC CALC®Engineering Report Dry 108-00-00 April 10, 2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) • Shear(Ibs) - Total Defl. (in) Reaction(lbs) 2284 Compression (psi) Loadcase#2: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 54.81 lbs --- Point Load Dead Load 00-00-00 -- 1607.00 lbs --- Point Load Snow Load 00-00-00 ---- 1556.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl. (in) Reaction(lbs) 3218 Compression(psi) Loadcase#3:(1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 54.81 lbs --- Point Load Live Load 00-00-00 ---- 622.00 lbs ---- Point Load Dead Load 00-00-00 -- 1607.00 lbs --- Point Load Snow Load 00-00-00 --- 1556.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 3295 Compression(psi) Page 30 of 38 aBoise Cascade lllII Double 2 x 4 DFL SS ENOINFFRFr)WOOD PRODUCTS Post 6 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.5" lex=08-00-00 Kf=0.75 Slenderness Ratio x=32.00 c=0.80 Eccentricity y=0.58" ley=08-00-00 Ke= 1.00 Slenderness Ratio y=27.43 . Factored Product Data ` Ex= 1.90 x 106 psi Ey= 1.90 x 106 psi lx=5.36 in4 FDEX=554.20 psi FbE=6026.78 psi Eminx=0.69 X 106 psi Eminy=0.69 X 106 psi ly=0.98 in4 FcEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.22 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) 1108 Reaction(lbs) Compression(psi) Compression and Bending(%) 12.8 12 Load cases Loadcase#0:(1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 19.25 lbs ---- , Point Load Dead Load 00-00-00 --- 540.00 lbs -- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 559 Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 19.25 lbs -- Point Load Live Load 00-00-00 --- 209.00 lbs --- Point Load Dead Load 00-00-00 -- 540.00 lbs --- Page 31 of 38 r __ ® - Double 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 6 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) • Shear(Ibs) Total Defl.(in) Reaction (lbs) 768 Compression(psi) Loadcase#2: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 19.25 lbs --- Point Load Dead Load 00-00-00 ---- 540.00 lbs --- Point Load Snow Load 00-00-00 --- 523.00 lbs -- Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl. (in) Reaction (lbs) 1082 Compression(psi) Loadcase#3: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 19.25 lbs ---- Point Load Live Load 00-00-00 --- 209.00 lbs --- Point Load Dead Load 00-00-00 --- 540.00 lbs ---- Point Load Snow Load 00-00-00 --- 523.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction (Ibs) 1108 Compression(psi) Page 32 of 38 ®Boise Cascade' Triple2x4DFLSS WOOD PRODUCTS ENGINEERED Post 7 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.75" lex=08-00-00 Kr=0.75 Slenderness Ratio x=21.33 c=0.80 Eccentricity y=0.58" ley=08-00-00 Ke= 1.00 Slenderness Ratio y=27.43 Factored Product Data EX= 1.90 x 106 psi Ey= 1.90 x 106 psi lx=5.36 in4 FLEX= 1246.95 psi FbE=9040.17 psi Eminx=0.69 x 106 psi Eminy=0.69 X 106 psi ly=0.98 in4 FcEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.38 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 4189 Compression(psi) Compression and Bending(%) 33.2 27.3 Load cases Loadcase#0:(1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 28.88 lbs -- , Point Load Dead Load 00-00-00 --- 1837.00 lbs -- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) 1866 Reaction(Ibs) Compression(psi) Loadcase#1: (1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 28.88 lbs -- Point Load Live Load 00-00-00 --- 1542.00 lbs ---- Point Load Dead Load 00-00-00 -- 1837.00 lbs ---- Page 33 of 38 Triple 2 x 4 DFL SS ENWEERED woof)PRoDucra Post 7 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) • Shear(lbs) Total Defl. (in) Reaction (Ibs) 3408 Compression (psi) Loadcase#2: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 28.88 lbs --- Point Load Dead Load 00-00-00 --- 1837.00 lbs --- Point Load Snow Load 00-00-00 -- 1556.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 3422 Compression(psi) Loadcase#3: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 28.88 lbs --- Point Load Live Load 00-00-00 ---- 1542.00 lbs -- Point Load Dead Load 00-00-00 -- 1837.00 lbs ---- Point Load Snow Load 00-00-00 -- 1556.00 lbs --- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 4189 Compression(psi) Page 34 of 38 Boise Cascade' Double 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 8 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.5" lex=08-00-00 Kr=0.75 Slenderness Ratio x=32.00 c=0.80 Eccentricity y=0.58" ley=08-00-00 KB= 1.00 Slenderness Ratio y=27.43 Factored Product Data Ex= 1.90 x 106 psi Ey= 1.90 x 106 psi Ix=5.36 in4 FGEx=554.20 psi FbE=6026.78 psi Eminx=0.69 X 106 psi Eminy=0.69 X 106 psi ly=0.98 in4 FcEy=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 115% 115% Moisture Content 1.00 Column Stability 0.22 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 2036 Compression(psi) Compression and Bending(%) 36.5 35.9 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 19.25 lbs -- Point Load Dead Load 00-00-00 --- 770.00 lbs Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl.(in) Reaction(Ibs) 789 Compression(psi) Loadcase#1:(1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 19.25 lbs --- Point Load Live Load 00-00-00 --- 1139.00 lbs -- Point Load Dead Load 00-00-00 --- 770.00 lbs --- Page 35 of 38 . a Double 2 x 4 DFL SS ENGNEERED WOOD PRODUCTS Post 8 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) • Shear(Ibs) - Total Defl.(in) - Reaction(Ibs) 1928 Compression(psi) Loadcase#2: (1.00D+1.00S) 1.00 Dead Load+ 1.00 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 19.25 lbs -- Point Load Dead Load 00-00-00 ---- 770.00 lbs --- Point Load Snow Load 00-00-00 ---- 523.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(lbs) 1312 Compression(psi) Loadcase#3: (1.00D+0.75S+0.75L) 1.00 Dead Load+0.75 Live Load axial+0.75 Snow Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 --- 19.25 lbs --- Point Load Live Load 00-00-00 — 1139.00 lbs --- Point Load Dead Load 00-00-00 --- 770.00 lbs ---- Point Load Snow Load 00-00-00 --- 523.00 lbs ---- Front-Back Left-Right Axial Bending(ft-lbs) Shear(lbs) Total Defl. (in) Reaction(Ibs) 2036 Compression (psi) Page 36 of 38 ®Bo1seCascadeDouble 2 x 4 DFL SS ENGINFPGPS WOOD PRODUCTS Post 9 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 General Data Eccentricity x=0.5" le.=08-00-00 Kr=0.75 Slenderness Ratio x=32.00 c=0.80 Eccentricity y=0.58" ley=08-00-00 Ke= 1.00 Slenderness Ratio y=27.43 • Factored Product Data EX= 1.90 x 106 psi Ey= 1.90 x 106 psi Ix=5.36 in4 FcE:=554.20 psi FbE=6026.78 psi Emimc=0.69 x 106 psi Eminy=0.69 X 106 psi ly=0.98 in4 Fcey=754.33 psi Modification Factors Front-Back Left-Right Factor Compression Bearing Moment Shear Moment Shear Load Duration 100% 100% Moisture Content 1.00 Column Stability 0.22 Lateral Stability Repetitive Member Size 1.50 Maximum Values Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl.(in) Reaction(Ibs) 1616 Compression(psi) Compression and Bending(%) 25.7 25 Load cases Loadcase#0: (1.00D) 1.00 Dead Load Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 -- 19.25 lbs -- r Point Load Dead Load 00-00-00 -- 834.00 lbs ---- • Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) Total Defl. (in) Reaction(Ibs) 853 Compression(psi) Loadcase#1:(1.00D+1.00L) 1.00 Dead Load+ 1.00 Live Load axial Load Type Component Start Pos End Pos Start Value End Value Point Load Dead Load 00-00-00 ---- 19.25 lbs --- Point Load Live Load 00-00-00 -- 763.00 lbs --- Point Load Dead Load 00-00-00 ---- 834.00 lbs --- Page 37 of 38 ®BoiseCascader Double 2 x 4 DFL SS ENGINEERED WOOD PRODUCTS Post 9 BC CALC®Engineering Report Dry 108-00-00 April 10,2023 22:05:12 Build 16959 Front-Back Left-Right Axial Bending(ft-lbs) Shear(Ibs) • Total Defl. (in) Reaction(Ibs) 1616 • Compression(psi) e Page 38 of 38