Permit MCITY OF TIGARD REROOF PERMIT
I
COMMUNITY DEVELOPMENT Permit#: RER2023-00001
TIGARD 13125 SW Hall Blvd.,Tigard OR 97223 503.718.2439 Date Issued: 1/12/2023
Parcel: 1S135CA00600
Jurisdiction: Tigard
Site address: 11200 SW GREENBURG RD, UNIT#22
Project: Autumn Oaks Apartments Subdivision: GREENBURG Lot: 11
Project Description: Remove(1)layer of existing roof and install new roof system for units 22&24.
Contractor: CARLSON ROOFING CO INC Owner: AUTUMN OAKS PROPERTIES LLC
PO BOX 1695 BY BLUESTONE& HOCKLEY
HILLSBORO, OR 97123 4915 SW GRIFFITH DR#300
BEAVERTON, OR 97005
PHONE: 503-846-1575 PHONE:
FAX: 503-640-2122
FEES
Description Date Amount
Permit Fee 01/12/2023 $985.47
Specifics: 12%State Surcharge-Building 01/12/2023 $118.26
Type of Use: COM
Class of Work: ALT Type of Const:
Occupancy Load:
Stories: Height: 0 ft
Project Valuation: $83,852.00
General Information
Building Area: 0
Re-Roof Area: 0
Roof Class:
Tear Off:
Overlay:
Existing Roof Layers:
Parapets:
Total $1,103.73
Required Items and Reports(Conditions)
This permit is issued subject to the regulations contained in the Tigard Municipal Code, State of OR. Specialty Codes and all other applicable law. All work
will be done in accordance with approved plans. This permit will expire if work is not started within 180 days of issuance, or if work is suspended for more
the 180 days. ATTENTION: Oregon law requires .0 to follow the rules adopted by the Oregon Utility Notification Center. Those rules are set forth in OAR
952-001-0010 through OAR -001 090. u m. •btain a -..y of the rules or direct questions to OUNC by calling 50 32.1987 or 1.800.332.2344.
r
Issued By: /j,� Permittee Signature: / 44. �+
j
Call 503.639.4175 by 7:00 a.m.for the next available inspection date.
This permit card shall be kept In a conspicuous place on the job site until completion of the project.