Report (2) EcoFusten
For InstaHers. By Installers.
COMPLETE RAIL - BASED
RACKING SYSTEM
INSTALLATION GUIDE
Osten,
GUIDEINSTALLATION
Clicking the page name will take you to that page
TABLE OF CONTENTS PAGE 01
.......................................................................................................................................
FEATURES & BENEFITS PAGE 02
.......................................................................................................................................
INTRODUCTION PAGE 03
OVERVIEW PAGE 04
COMPONENTS ................................................................PAGE 05
RATINGS PAGE 06
ARRAY LAYOUT PAGE 07
N STALLAT.I.O N..................................................................PAG.E. 08
GROUNDING PAGE 17
ACCESSORI.ES......................................................................PAG.E...21..
MODULE LIST......................................................................PAGE 27
CLAM P..PART..N.0 M.B.ERS.........................................PAG.E. 36
1
INSTALLATION , 1 1 asten,
For -
CLICKFIT
ClickFit conforms to UL 2703 and is one of the fastest installing rail-based systems in
the industry. Thanks to its Click-In Rail assembly, the rails can be connected to any of
EcoFasten's composition shingle, tile, and metal roof mounts in seconds without theF
need for fasteners or tools. The ClickFit system is made of robust materials, such as
aluminum and coated steel, to ensure corrosion resistance and longevity. ClickFit has
been tested in extreme weather conditions including wind, fire, and snow.
FEATURES
• Tool and fastener free rail attachment
• Fully integrated bonding
• Click-on Mid & End Clamps
• Compatible with a variety of EcoFasten roof attachments
INSTALLATION GUIDE 0 a S e n,
For Installers. By InstaRers.
INTRODUCTION
This manual describes the installation of the ClickFit mounting system for
photovoltaic modules on steep-slope roofs. Described within are details for
composition shingle and tile, attachments for ClickFit System. Other roof types
as well as all other installation manuals can be found for download at www.
EcoFastenSolar.com.
GENERAL INSTALLATION CONDITIONS
Failure to observe the requirements in this document can lead to the exclusion of
all guarantees and product liability. EcoFasten Solar reserves the right to amend this
document without prior notice.
STABILITY AND CONDITION OF THE ROOF
The roof must be in good condition and strong enough to support the weight of the
modules, including the additional equipment, wind and snow loads. When in doubt,
consult with the engineer of record, and/or the local building inspector.
APPLICATION RANGE OF CLICKFIT
Refer to Compatibility module list at the end of this document. Please refer to the
Ecofasten ClickFit span tables for system structural certification and allowable spans.
WARRANTY
Guarantee according to the warranty conditions and general terms and conditions
of EcoFasten Solar. These conditions can be found on the website at www.
EcoFastenSolar.com.
LIABILITY
EcoFasten Solar cannot accept any liability whatsoever for damage or injury caused
by not taking adequate safety precautions or (accurately)following the instructions
given, or resulting from negligence during the installation of the product and any
corresponding accessories specified in this document.
INSTALLATION GUIDE •
n:
OVERVIEW
The ClickFit mounting system consists of patented adjustable tile hooks and L
feet, rails, and the installation materials required for the mounting of photovoltaic
modules on composition shingle or tile roofs. For simplicity, tile hooks and L feet will
be referred to as"attachments".
ATTACHING TO THE ROOF
The attachments are fastened to the rafters. Attachments are height-adjustable to
level the system on uneven roof surfaces.
Z7
ATTACHING THE RAIL
The rail assembles to the attachments with a click-connector, or Clicker. The rail
simply clicks into place without the use of any tools.
ATTACHING THE MODULES
The modules are attached to the rails by means of mid clamps and end clamps.
Installer must review module and any 3rd party manufacturer's documentation for
compatibility and compliance with warranty terms and conditions.
INSTALLATION , E EcoFasten ,
For Installers. By Instatters.
SYSTEM COMPONENTS REQUIRED
CLICKFIT RAIL RAIL SPLICE TILE HOOK
41k
d
R
L-FOOT END CAP MID CLAMP
END CLAMP
SYSTEM COMPONENTS ACCESSORIES
AW X
FRAME MLPE MODULE JUMPER MLPE MOUNT
MOUNT
Refer to ClickFit Alternate Component Addendum for components not shown '
■
.;•, E c o F a s t e n
GUIDEINSTALLATION
For Installers, By Installers.
RATINGS
Fire Rating* Class A System Fire Rating
Max System Voltage 1500 VDC
Max Fuse Rating 40A
Certification Conforms to UL STD 2703
Warranty 25 Year Material and Workmanship
UL 2703 Markings Product listing label is located on the rail end-caps
Roof Pitch 2:12-12:12
UL 2703 Allowable design Load Rating 10 psf downward,5 psf upward,and 5 psf lateral
Max Module Size 25.6 sqft
Module Orientation Portrait or Landscape
Multiple use Rated Components(Position Independent) Mid Clamp,Frame MLPE Mount and MLPE Mount
*Class A System fire rating with Type 1 &2 PV modules.Any module-to-roof gap is permitted,with no skirt required.This rating is
applicable with any roof attachment.
UL 2703 MARKING EXAMPLE:
EcoFasten
ESIDECCompany
us
CLICKFIT
Intertek
iSYSTEM
MFG ID CODE: .. XXXXXXX »
got-
TORQUE SPECIFICATIONS
m
T
Component Torque(in-lb) Notes
Lag Screw N/A Fully Seat.Use visual indicator of the black EPDM ring around the
bonded washer for torquing.
Mid-Clamp 144
End-Clamp 96
Rail Clicker Leveling Bolt 142 Pre-torqued upon delivery.Applies to Tile Hook and L-Foot/Clicker
Hook Height Bolt N/A Lightly clamp hook to flush with top of next tile row
Ground Lug N/A Refer to specific ground lug manufacturer's installation manual
MLPE Clip 144
MLPE Mount 144
1
INSTALLATION GUIOE
EcoFasten.
For Insta[[eis. By InstatLers.
rr
• Refer to span tables, local jurisdiction, or engineer of record specifications
when determining setbacks from roof edges, attachment spans, etc.
• Mark the perimeter and corners of the array on the roof surface.
*Add 3/4" to account for the gap between modules in each direction*
• Draw or snap chalk lines where the rails will be installed,(refer to module
manufacturer specs to determine allowable mounting locations).
• Locate rafters within the area of the array. It may be necessary to shift
the array East or West on the roof in order to fall within the rail cantilever
specs (1/ 3 of span).
• Stagger rafters every row if required by the local jurisdiction, engineer of
record, or company policy.
1
INSTALLATION GUIDE EcoFasten,
For InstaLters. By InstaLLers.
PRE-INSTALLING RAIL SPLICES
1. Determine the number of rails required per row of modules.
2. Insert a rail splice into one rail. Do not push it past the center bump.
3. Slide the next rail onto the rail splice until the two rail ends meet.
4. Repeat steps 2 and 3 until the desired length is achieved. This is usually
easiest to do from the ground.
i
1
INSTALLATION GUIDE De C 0 as en,.
INSTALLATION OF FLASHING & L-FOOT
• ClickFit for comp shingle roofs uses EcoFasten GF-1
watertight flashing system.
e �
• Other roof types may use different EcoFasten Solar
attachments, visit ecofastensolar.com to learn
` about other applications.
*Note the orientation of the L foot and Clicker.The two
Clicker"arms"should be facing downslope*
INSTALLATION STEPS:
�./ 3 ~i
10
1. Locate rafter lines.
2. Drill 1/4" pilot holes at all attachment points and back fill using roof-
compatible sealant.
3. Separate shingles where flashing is to be installed. Insert the flashing so the
top portion is under the next row of shingles North. Ensure the flashing is
pushed to the third-course of shingle to prevent water infiltration through
the vertical joints between shingles.
4. Align GF-1 flashing hole with pilot hole. Insert the lag bolt with pre-installed
bonded washer through the L foot and EPDM grommet. Tighten the lag bolt
until fully seated. The EPDM Ring visual indicator is the most effective way to
ensure a watertight seal.
i
•
INSTALLATION , '.' EcoFasten,
Foi- Instatters. By Installers.
INSTALLING TILE HOOKS
1. Locate rafters on the roof, mark the tiles to be removed. Hint: In some cases rafter tails
are visible at the eaves of the roof, making it easy to find the rough location of the rafters.
In other cases,the fascia board may have nail heads visible where it was attached to the
rafters. In the worst-case a row of tiles may need to be moved to determine the rafter
locations.
2. Slide the tile at the desired location upward to expose the roof sub surface. If the tile is to be
notched, or if using a replacement flashing, remove it entirely. Clean the sub surface with a
brush to remove any debris that could affect the sealing.
3. Locate the rafter center and mark it.
4. Place the tile hook with the hook itself in the valley of the next tile below. Drill one 1/4"
pilot hole in the rafter center,taking care to keep the hook in the valley of the tile below.
Backfill this hole with a roof- compatible sealant. For flat tiles, try to avoid having the hook
land directly under a joint between tiles,this will create a larger gap or more notching than
necessary.
5. Install one 5/16"x 4'lag screw on the row of holes closest to the tile hook arm. If possible, Y
install the screw in one of the three holes directly next to the arm. If the lag screw must
be installed in one of the seven holes furthest from the arm(denoted by the red rectangle
below), install three deck screws in the pattern shown by the green circles below.
6. Adjust the height of the the hook as necessary using the bolt shown in the fourth image.
7. Flash the surrounding area and lag screw head with roof-compatible sealant as necessary.
Refer to Tile Hook Subflashing Installation guide on the next page.
8. Replace the the that was moved and/or removed, or install the tile replacement flashing.
If it is to be notched, mark the tile for notching. Notching can be done with a grinding
wheel or by using a chisel.
V
w,..�
6
- go
CLICK
_J
INSTALLATION GUIDE o0a EcoFasten:.
For Installers. By Installers.
Apply a continuous line of the roofing Lower the sub-flashing over the tile hook base.It may
manufacturer's approved sealant on the be necessary to move adjacent tiles to easily lower the
underside of the ClickFit tile hook sub-flashing sub-flashing onto the roof deck.
to form a U-shape around the raised edges.
w
t,
EcoFasten recommends following the TRI guidelines
Place the sub-flashing over the base of the tile hook so three-course sealing method.Start the three-course
Ile flashing covers the entire base. sealing method by applying a layer of roofing mastic
over the edges of the tile hook sub-flashing.
Place strips of reinforcing fabric over mastic to Apply a final layer of mastic to completely cove
cover approximately 2"from the edge of the he reinforcing fabric.The flashing is now installed PAG E
sub-flashing in both directions.Place strips on and sealed.
the side first,then the top edge. 11
INSTALLATION GUIDEOsten.
' ),' t
For InstaLLers. By InstalLers.
CLICKFIT INSTALLATION USING
SIMPLEBLOCK-U®
PRE-INSTALLATION:
The SimpleBlock-U can be installed on many different standing seam profiles. See SimpleBlock-U
Installation Manual for compatible and non-compatible standing seam profiles. Be sure that
each standing seam is no thicker than Yz"in width.
INSTALLATION:
O Position the SimpleBlock assembly on the panel
O seam. Make sure the block is fully seated on the
metal seam.
y O Torque the 2 preinstalled oval point set screws to
150in-lbs using the included 3116"hex drive.
2
OIncluded with the block, slide the hex holt into the w :
channel on top of the SimpleBlock-U assembly.
.t
O Place the ClickFit Universal L-Foot over the hex bolt
3 followed by the serrated flange nut and torque to
150in-lbs.
MAX
z z z
R
INSTALLATION GUIDE '241
For Installers. By Installers.
INSTALLING THE RAIL
1. Place the rail in the Clickers.
2. Ensure the rails extend a minimum
of 2" past the last attachments in
each row.
(k ? 3. Push the rail into each L-foot; an
audible click should be heard
when the rail is fully seated.
Verify the rail is sitting flush with
both ledges. If attachments are
------------
extremely misaligned it may be
necessary to loosen the leveling
bolt and adjust the height of the
L-foot. Tighten the clamping bolt
to 144 in-lbs. '
4. Level the rail if necessary by
loosening the bolt attaching the
Clicker to the L-foot or tile hook.
jj }
EcoFasten.
INSTALLATION GUIDE
For Instatters. By Instatters.
MODULE INSTALLATION
INSTALL THE END CLAMPS ON EACH RAIL ON
WHATEVER END YOU ARE STARTING WITH
�a Snap the end clamp onto the rail.
'b Slide the end cap onto the rail.
8 Turn the leg of the end clamp around the cap.
O PLACE MODULE
Place the module on the rail, ensuring
the module junction box
is up-slope.*
2 Q ALIGN AND TIGHTEN
Slide the module to the end clamp and
align it with the array corners. Tighten
~~ the end clamp to 96 in-Ib
3 ' '
INSTALLATION
�.. EcoFasten,
Foi Installers. By Installers.
INSTALLING ADDITIONAL MODULES
O CLICK IT ON
Click a mid clamp onto each rail.
e
Q SLIDE IT UP
Slide the mid clamps until they are
flush with the side of the existing
module.
a PLACE AND TIGHTEN
Place and slide the next module firmly
� n
against the mid clamps. Align the
bottom edges of the modules.Tighten
mid clamps to 144 in-Ib.
}
'Z� k
6
3
1
INSTALLATION GUIDE .,. Ec 0 Fa ste n,
For Installers. By Instatters.
INSTALLING END CLAMPS
AT THE END OF A ROW
1. Install the last mid clamps in the row.
2. Measure the rails from the last mid clamp to the module width plus 1".
3. Cut the rails at this mark. There is some adjustment in the end cap/clamp so it does not
need to be a perfect cut.
4. Install end clamps and end caps,tighten to 96 in-Ib
ALTERNATIVE METHOD:
1. Install the last module in the row,tighten the mid clamps.
2. Using a circular saw with a metal blade, or carefully with a reciprocating saw, cut the rail
approximately 1" past the edge of the last module.
3. Install end clamps and end caps, tighten to 96 in-lb
Replace the tile that was moved and/or removed, or install the tile replacement flashing. If it
is to be notched, mark the the for notching. Notching can be done with a grinding wheel or by
using a chisel.
\.�\
\ 7
\ ` ~X ,>`'
INSTALLATION GUIDE
EcoFasten,.
For Instalters. By Instatters.
BONDING AND GROUNDING
BONDING PATHS
Bonding paths are carried throughout the array in a variety of ways. They are carried module-
to-module and module-to-rail through mid clamps, carried at rail-to-rail connections through
the bonding jumpers, and carried row-to-row using bonding jumpers either module-to-module
on the module frame or rail-to-rail on the ends of the rails.
MID CLAMP
2 mid clamps bonding
pairs of modules
GROUNDING LUG
1 ground lug per
continuous array
r
C3
RAIL SPLICE
1 splice bonding
MODULE JUMPER adjacent pair of rails
1 module jumper
bonding module to
module and row to row
A EcoFasten.
.•••.
INSTALLATION 1
For Instalters. By Installers.
GROUNDING
� s
E
ri
NECESSARY COMPONENTS
One of the following grounding lugs(or any UL 2703 Compliant ground Lug):
• BurndyCL50-1TN Ground Lug(UL 2703 - E3514343/ UL 467-E9999)
• ILSCO SGB-4 Ground Lug(UL 2703 - E354420/UL 467- E34440)
• ILSCO GBL-4DBT(UL 2703 - E354420/ UL467 - E34440)
• ILSCO GBL-4DBTH (UL 2703 - E354420/ UL 467 - E34440)
• ILSCO GBL-4SS(UL 2703 - E354420/ UL 467 - E34440) v
*Equipment grounding wire should be sized in accordance with the National Electrical Code,NFPA70
and a minimum of 1/4"clearance is required between bare copper wires and aluminum components.
•
CLICK
e
INSTALLATION GUIDE oOa E c o F a s t e n
For Installer By Installers.
v
Lower the MLPE Mount to the rail Tilt and hook the mount around
the top"dog ear"of the rail
Set the MLPE Mount flush with the top of the rail Slide the microinverter flange between the
MLPE Mount and the serrated bolt flange
Tighten the bolt to 144 in-lbs Repeat this process for all other microinverter
and/or optimizer installations
PAGE
19
CLICK
DSV
INSTALLATION GUIDE oCEcoFasten
For Installers. By Installers.
With the ClickFit Rail in
place and the Wire Clip
in hand, place the wire
end on either side of the
rail. With the wire end
touching the bottom lip
of the rail, roll and click-
in the Wire Clip to the
opposite end of the rail.
You will hear an audible
click when the Wire Clip
is set in place.
PAGE
20
M-
INSTALLATION GUIDE
.:•• coFasten,
FRAME MLPE MOUNT
�y
INSTALLING THE FRAME MLPE MOUNT ACCESSORY:
• Install the Frame MLPE Mount
• Slide the Frame MLPE Mount onto the lip of the micro-inverter/power optimizer.
• Slide the micro-inverter/power optimizer into the opposite lip of the module frame.
• Tighten the bolt to 144 in-Ib to clamp the Frame MLPE Mount to the module frame and the r
micro-inverter/power optimizer to the Frame MLPE Mount.
• Ensure that the lip on the clip is tight against the frame and that the micro-inverter/power
f 3f,i
optimizer flange is tight against the clip flange to avoid rotation during tightening.
FRAME MLPE MOUNT AND MLPE MOUNT ARE COMPATIBLE WITH:
• ENPHASE: M250-72, 250-60, M215-60, C250-72, S230, 5280, IQ 6, IQ 6+, IQ7, IQ 7A, IQ 7+, IQ7
PD, IQ 7X, Q Aggregator; IQ8-60, IQ8PLUS-72, IQ8H-72, IQ81-1-208-72, IQ81-1-240-72, IQ8M-72,
may be followed by-2-US
• SOLAREDGE: M1600, P300, P320, P340, P370, P400, P401, P405, P485, P505, P600, P700, P730,
P800p, P800s, P801, P850, P860, P950, P960, P1100, P1101, S440, 5500
• SEE PAGE 26 FOR COMPATIBLE MODULE LIST
i
Y
INSTALLATION GUIDE
..•. EcoFasten,
For InstaHers. By InstaLlers.
MODULE MAINTENANCE AND SERVICING
During servicing or maintenance, module removal may disrupt the bonding path and
could introduce the risk of electric shock. If module removal is required for servicing, then
a Module Jumper shall be installed to the adjacent modules to maintain the bond path.
Modules should only be removed by qualified persons in compliance with the instructions
in this manual.
�r
� x
--- Bond Path
Grounding Lug C3
Equipment Grounding
Conductor(EGC)
generally to earth
ground
Brackets/Mid-Clamps
Modulejumper
r
■
INSTALLATION GUIDE ' Dt C 0 asten.
For InstalLers. By InstaLlers.
JUNCTION BOX INSTALLATION
f
i
JUNCTION BOX PREP
Prior to installation, use step drill bit to place pass through holes for conduits or
water-tight connectors. Drill bit starter locations are provided on the sides and front
of enclosure. Do not install conduit facing up roof.
d�
1�r
RAIL INSTALLATION
Use rail-specific MLPE mounting hardware to attach Rail Hangers to rail. Ensure
junction box is pushed as close to the rail as possible.Torque to 80-in Ibs(1/2"or 7/16"
socket), do not overtighten.
*lf installing in areas with ground snow loads greater than 40 psf,install junction Box under module directly next to module
frame edge.
INSTALLATION GUIDE ''O)"' C / asten,
JUNCTION BOX INSTALLATION
DECK SCREWS WITH
SEALING WASHERS(M
DECK MOUNTED INSTALLATION
Align sealing oval of box to align with mating feature on flashing.An EPDM foam gasket is
pre-installed to the underside of the junction box to seal the flashing to the box without
the need for additional sealant. Secure with supplied#12 x 1- "deck screws(2x)until the
junction box is pulled tight to the flashing. Do not over-tighten screws to avoid stripping
screws in OSB.
*If installing pass through fittings,ensure that theJunction Box and roof deck are both properly prepared.Complete installation
process before attaching the Junction box to the deck.
6
FINALIZING INSTALLATION
Install wiring, conduit and fittings per NEC requirements and following local AHJ guidance.
Using Philips Head Driver tighten the bolt.
For additional details refer to the full Junction Box Installation Manual.
INSTALLATION GUIDE1,Cr EcOF us ten
• -
SKIRT INSTALLATION (OPTIONAL)
The skirt is designed to give the rows of the array facing the eave of the roof a uniform
appearance.The installation consists of three basic components listed below.
SKIRT& END CAP t SKIRT CLAMP
1. Once the first row of modules is installed (or after the array is complete ), locate the correct
length and number of skirts for the array.
2. Locate the correct amount of skirt clamps for the array. 80"skirts are preferred when
applicable.The general rule when using 80"skirts is the number of modules plus one for the
end of the array. When using 6S skirts, the rule changes to 2 skirt clamps per module.The
general rule is number of modules plus one for the end of the array. If you have ten modules
you will need eleven skirt clamps. In the case of heavy snow loads or other circumstances call
EcoFasten Solar for additional instructions.
3. Working with a helper, align the end of the skirt with one edge of the array, drop the first skirt
clamp onto the module and skirt, ensure all flat faces are parallel and fully engaged with each
other. Skirt clamps must be installed within 10 inches from the end of the Skirt. Ensure the ° *z '
clamp is engaging either the top of the skirt or the step depending on the module size. Tighten
bolt to 12 ft-Ib.
4. There should be enough play in the assembly to drop the next skirt clamp onto the next
module at roughly the same location relative to the clamp on the last module. Ensure all
faces are parallel and fully engaged with each other. Slide next skirt over the skirt end cap or
coupling of the first skirt. Tighten bolt to 12 ft-Ib. N
S. Repeat steps 3 and 4 until the end of the array is reached. Install a skirt clamp within 10
inches from the end of the array. Cut the skirt flush with the end of the array as necessary.An
additional skirt clamp may be necessary to hold a short piece of skirt at the end of the array.
6. Once the last skirt is cut and clamped in place, install an end cap in the end of the last skirt. To
ensure the end cap stays in place through various weather conditions, it is acceptable to install
a small amount of roof sealant onto the edge of the end cap that will contact the inside face `s
of the skirt. Replace the tile that was moved and/or removed, or install the tile replacement
flashing. If it is to be notched, mark the tile for notching. Notching can be done with a grinding
wheel or by using a chisel.
INSTALLATION GUIDE
;••
EcoFasten
For Instalters. By Installers.
Install first skirt clamp within 10 inches from
the end of the array with 80"skirts, the second
clamp location will be similar to the first clamp
but installed on the second module. Continue to
` the end of the array.
r
ter' h
Install last skirt clamp within 10 inches from the
Fy end of the array prior to cutting.
. m 6
' Install end cap on the last module.Adding a `
0
small amount of sealant is optional.
s' A
THINGS TO CONSIDER PRIOR TO INSTALLING THE SKIRT ARE:
• Potential snow drifting in the area the skirt is to be installed. If the snow load is greater
than 20psf in your region two skirt clamps are required per module and skirt coupler must
be used. Contact EcoFasten for information on the skirt coupler.
• There are three options for skirts:A, B and C. The A& B skirts can be identified by looking
at the inner channel, if it's ribbed then it is a B skirt and will use 32mm (inner channel)
and 38mm utilizing the top of the skirt. A skirts will have a smooth inner channel and use
35mm (inner channel) and 40mm utilizing the top of the skirt. C skirts will only use 30mm
skirts and do NOT have an inner channel.
INSTALLATION ,
.,. E c o F a s t e n
For Installers. By Installers.
UL 2703 CERTIFIED MODULES
This racking system may be used to ground and/or mount a PV module complying with UL
1703 or UL 61730 only when the specific module has been evaluated for grounding and/or
mounting in compliance with the included instructions.
Unless otherwise noted, "xxx" refers to the module power rating and both black and silver
frames are included in the certification.
MANUFACTURER LIST OF APPROVED •
Adani modules with 35 and 40mm frames
AdamASX-Y-ZZ-xxx
Where"X"can be B, M or P,"Y"can be 6 or 7, and"ZZ"can be blank, PERC,
B-PERC, or AB-PERC
Aionrise modules with 35 and 40mm frames
Aionrise Al0NyyG1-xxx
Where"yy"can be 60 or 72
Amerisolar modules with 35,40 and 50 mm frames
AS-bYxxxZ
Amerisolar
Where"b"can be 5 or 6;"Y"can be M, P, M27, P27, M30, or P30; and Z
can be blank,W or WB
Aptos modules with 35 and 40 mm frames
Aptos Solar DNA-yy-zzaa-xxx
Where"yy"can be 120 or 144;"zz" can be MF or BF; and "aa" can be 23 or 26
Astronergy modules with 30, 35,40, and 45 mm frames
aaS M b byyC/zz-xxx
Astronergy Solar Where"aa"can be CH or A;"bb"can be 60, 66, or 72; "yy"can be blank, 10
or 12; "C"can M, P, M(BL), M-HC, M(BL)-HC, P-HC, M(DG), or M(DGT); and
"zz"can be blank, HV, F-B, or F-BH
ASUN modules with 35 and 40 mm frames
ASUN ASUN-xxx-YYZZ-aa
Where"YY"can be 60 or 72; "ZZ"can be M,or MI-15; and "aa"can be blank or
BB
Auxin modules with 40 mm frames
Auxin AXN6y6zAxxxB
Where"y"can be M or P; "z" can be 08, 09, 10, 11, or 12; and "A"can beF, M
or T; and "B"can be blank,A, B or C ,
Y
1
t
i ♦ �
MANUFACTUREREcoFasten:
INSTALLATION GUIDE
For InstaLLers. By InstaLLers.
' APPROVED
• • -
Axitec Modules with 30,35 and 40 mm frames
Axitec
AC-xxxY/aaZZb
�-
Where"Y"can be M, P or MH;"aa"can be blank, 125- or 156-; "ZZ"can be N
54, 60, 72, 108, 120, or 144; "b"can be S, X,V, VB, XV, or MX
Bouiet modules with 35 and 40mm frames
BVM66aaYY-xxxBcc
Boviet
Where"aa"can be 9, 10 or 12;"W"is M, or P; and"B"can be blank, L or S;
and "cc"can be blank, H, H-BF, H-HC, HC-BF or H-HC-BF
BYD modules with 35 mm frames
BYD BYDxxxAY-ZZ
Where"A"can be M6, P6, MH or PH; "Y"can be C or K; and"ZZ"can be 30 or
36
i
Canadian Solar modules with 30, 35 and 40 mm frames
Canadian Solar CSbY-xxxZ
Where"b"can be 1, 3 or 6;"Y"can be H, K, L, N, P, U,V, W,X or Y; and "Z"
can be M, P, MS, PX, M-SD, P-AG, P-SD, MB-AG, PB-AG, MS-AG, or MS-SD
E
CertainTeed modules with 35 and 40mm frames
CertainTeed CTxxxYZZ-AA
Where"Y"can be M, P, or HC;"ZZ"can be 00, 01, 10, or 11; and "AA"can be
01, 02, 03, 04 or 06
Csun modules with 35 and 40 mm frames
CSUN YYxxx-zzAbb
Where"YY"is CSUN or SST;"zz" is blank, 60, or 72; and "A" is blank, P or M
or MM;"bb" is blank, BB, 5BB, BW, or ROOF
Dehui modules with 35 and 40mm frames
Dehui DH-MYYYZ-xxx
Where"YYY"can be 760, 772, 860, 872; and"Z"can be B or W
Ecosolargy modules with 35, 40, and 50 mm frames
Ecosolar ECOxxxYzzA-bbD
Where"Y"can be A, H, S, or T;"zz"can be 125 or 156; "A"can be M or P;"bb"
can be 60 or 72; and "D"can be blank or B
ET Solar modules with 35,40, and 50 mm frames
ET-YZZZxxxAA
�x1sk
ET Solar Where"Y"can be P, L, or M; "ZZZ"can be 660, 66013H, 672, 67213H, 754BH
or 766BH; and "AA"can be TB,TW, WB,WW, BB,WBG, WWG, WBAC,WBCO,
WWCO,WWBCO or BBAC
•
3t
3
ti EcoFastenINSTALLATION ,
'.'
Foi Installers. By InstaLlers.
MANUFACTURER LIST OFUL 2703 APPROVED •
Flex modules with 35,40, and 50 mm frames
FXS-xxxYY-ZZ;
Flex
Where"YY"can be BB or BC; and "ZZ"can be MAA1 B, MAA1 W, MA131 W,
SAA1 B, SAA1 W, SAC1 B, SAC1 W, SAD1 W, SBA1 B, SBA1 W, SBC1 B, or SBC1 W
GCL modules with 35 mm and 40 mm frames
GCL GCL-ab/YY xxx
Where"a"can be M or P;"b"can be 3 or 6; and "YY"can be 60, 72, 72H, or
72DH
Gigawatt modules with 40 mm frames
GigaWatt Solar GWxxxYY
Where"YY"can be either PB or MB
Hansol modules with 35 and 40 frames
Hansol HSxxxYY-zz
Where'YY"can be PB, PD, PE,TB,TD, UB, UD, or UE; and "zz"can be AH2, Cn
# AN1, AN3,AN4, HH2, HV1, or JH2
Hanwha Solar modules with 40,45, and 50 mm frames LU
Hanwha Solar HSLaaP6-YY-1-xxxZ
Where"aa"can be either 60 or 72; "YY"can be PA or PB; and "Z"can be
blank or B
Hanwha Q CELLS Modules with 32, 35, 40, and 42mm frames
aaYY-ZZ-xxx
(where"aa"can be Q. or B.;"YY"can be PLUS, PRO, PEAK, LINE PRO, LINE
PLUS, PLUS DUO or PEAK DUO; and "ZZ"can be G3, G3.1, G4, G4.1, L-G2,
L-G2.3, L-G3, L-G3.1, L-G3y, L-G4, L-G4.2, L-G4y, LG4.2/TAA, BFR-G3, BLK-G3,
BFR-G3.1, BLK-G3.1, BFR-G4, BFR-G4.1, BFR G4.3, BLK-G4.1, G4/SC, G4.1/
j SC, G4.1/TAA, G4.1/MAX, BFR G4.1/TAA, BFR G4.1/MAX, BLK G4.1/TAA, BLK
Hanwha Q CELLS G4.1/SC, EC-G4.4, G5, G5/SC, G5/TS, BLK-G5, BLK-G5/SC, BLK-G5/TS, L-G5,
L-G5.1, L-G5.2, L-G5.2/1-1, L-G5.3, G6, G6/SC, G6/TS, G6+, BLK-G6, L-G6,
L-G6.1, L-G6.2, L-G6.3, G7, BLK-G6+, BLK-G6+/AC, BLK-G6+/HL, BLK-G6+/SC,
BLK-G6/TS, G6+/TS, BLK-G6+/TS, BLK-G7, G7.2, G8, BLK-G8, GB+, BLK-G8+
L-G7, L-G7.1, L-G7.2, L-G7.3, L-G8, L-G8.1, L-G8.2, L-G8.3, L-G8.3/BFF, ML-G9,
BLK ML-G9, ML-G9+, BLK ML-G9+, BLK-G10+, BLK-G10+/AC, ML-G10, BLK
ML-G10, ML-G10+, BLK ML-G10+, ML-G10.a, BLK ML-G10.a, ML-G10.a+, BLK
ML-G10.a+, XL-G9, XL-G9.2, XL-G9.3,XL-G10.2, XL-G10.3, XL-G10.c or XL-
G10.d
•
t
INSTALLATION GUIDE
�.. co asten
•
MANUFACTURER LIST OF • MODULES
Heliene modules with 40 mm frames
YYZZxxxA -
Heliene
Where"YY"can be 36, 60, 72, 96, 120 or 144; "ZZ"can be HC, M, P, or MBLK;
and"A"can be blank, HomePV, or Bifacial
HT-SAAE modules with 35 and 40 mm frames
HT-SAAE HTyy-aaaZ-xxx
Where"yy'can be 60, 66 or 72; "aaa"can be 18, 156 or 166;"Z"can be M, P,
M-C, P-C, M(S), M(VS), M(V), P(V), M(V)-C, P(V)-C, or X
Hyundai modules with 33, 35, 40 and 50 mm frames
Hyundai HiY-SxxxZZ
Where"Y"can be A, D or S;"S"can be M or S; and "ZZ' can be HG, HI, KI, MI,
MF, MG, PI, RI, RG, RG(13F), RG(BK), SG,TI or TG
Itek Modules with 40 and 50 mm frames
Itek IT-xxx-YY
Where"YY"can be blank, HE, or SE, or SE72
JA Solar modules with 30, 35,40 and 45 mm frames
JAyyzz-bbww-xxx/aa
Where"yy'can be M, P, M6 or P6; "zz"can be blank, (K), (L), (R), (V), (BK), (FA),
JA Solar (TG), (FA)(R), (L)(BK), (L)(TG), (R)(BK), (R)(TG), (V)(BK), (BK)(TG), or(L)(BK)(TG);
"bb"can be 48, 54, 60, 66, 72 or 78;"ww"can be D09, S01, S02, S03, S06,
S09, S10, S12, S17, S20, S30 or S31; and"aa"can be 1313, MR, SI, SC, PR, 3136,
4BB, 4BB/RE, 513B
Jinko modules with 35 and 40 mm frames
JKMYxxxZZ-aa
Where"Y"can either be blank or S; "ZZ"can be M, P, or PP; and"aa"can be
Jinko blank, 60, 60B, 60H, 60L, 60BL, 60HL, 60HB, 60HBL, 6HBL-EP, 60-J4, 6013 J4,
60B-EP, 60(Plus), 60-V, 60-MX, 6RL3, 6RL3-B, 6TL3-B, 7RL3-V, 7RL3-TV, 72,
72B, 72-J4, 7213 J4, 72(Plus), 724, 72H-V, 72L-V, 72HL-V, 72-MX, 72H-BDVP,
72HL-TV, or 72HL-V-MX3
Kyocera Modules with 46mm frames
KYxxxZZ-AA
Kyocera Where"Y"can be D or U;"ZZ"can be blank, GX, or SX; and "AA"can be LPU,
LFU, UPU, LPS, LPB, LFB, LFBS, LFB2, LPB2, 3AC, 313C, 3FC, 4AC, 413C, 4FC,
4UC, 5AC, 513C, 5FC, 5UC, 613C, 6FC, 8BC, 6MCA, or 6MPA
LG modules with 35,40,and 46 mm frames
LG LGxxxYaZ-bb
Where'Y"can be A, E, M, N, Q,S;"a"can be A, 1,2or3;"Z"can be C, K,T,or W;
' and"bb"can be A3,A5,A6, 133, 136, E6, E6.AW5,G3,G4,J5, K4, L5, N5,V5,V6
INSTALLATION EcoFasten
GUIDE ',•�'
For Instalters. By InstaLlers.
MANUFACTURER LIST OF • MODULES
Longi modules with 30, 35 and 40 mm frames
Long! LRa-YYZZ-xxxM
Where"a"can be 4 or 6; "YY"can be blank, 60, 66 or 72; and "ZZ"can be
blank, BK, BP, HV, PB, PE, PH, HBD, HIB, HIH, HPB, HPH, or HIBD
Mission Solar modules with 33, 35 and 40 mm frames
[YYYbb-xxxZZaa
Mission Solar Where"YYY"can be MSE or TXS; "bb"can be blank, 6 or 60A; "ZZ"can be
blank, MM, SE, SO, SQ , SR, SX, TS, 120 or 144; and "aa"can be blank, BB,
BW, 1J, 4J,4S, 5K, 5R, 5T, 60, 6J, 6S, 6W, 6Z, 8K, 8T, or 9S
Mitsubishi modules with 46 mm frames
Mitsubishi PV-MYYxxxZZ
Where"YY"can be LE or JE; and "ZZ"can be either HD, HD2, or FB
MOtech IM and XS series modules with 40, 45, and 50 mm frames
Next Energy Next Energy Alliance modules with 35 and 40mm frames
Alliance yyNEA-xxxZZ
where"yy"can be blank or US; "ZZ"can be M, MB or M-60
Neo Solar Power modules with 35 mm frames
Neo Solar Power D6YxxxZZaa
I Where"Y"can be M or P; "ZZ"can be 133A, B4A, E3A, E4A, H3A, H4A; and "aa"
can be blank, (TF), ME or ME (TF)
Panasonic modules with 35 and 40 mm frames
Panasonic (HIT) VBHNxxxYYzzA
Where"YY"can be either KA, RA, SA or ZA;"zz"can be either 01, 02, 03, 04,
06, 06B, 11, 11 B, 15, 15B, 16, 16B, 17, or 18; and"A"can be blank E, GorN
Panasonic modules with 30 mm frames
Panasonic EVPVxxxA
(EverVolt)
Where"A"can be blank or H, K or PK
Peimar modules with 40 mm frames
SbxxxYzz
Peimar Where"b"can be G, M or P; "Y"can be M or P; and "zz"can be blank, (BF), or
(FB)
Philadelphia modules with 35 and 40 mm frames
PS-YzzAA-xxx
Philadelphia Solar
Where"Y"can be M or P; "zz"can be 60, 72 or 144; and "AA"can be blank,
(BF),(HC)or(HCBF)
PAGE
INSTALLATION GUIDE EcoF a sten
'D'
Foi Installers. By Installers.
MANUFACTURER LIST OF UL 2703 APPROVED MODULES
Phono Solar modules with 35,40, and 45 mm frames
Phono Solar PSxxxY-ZZ/A
Where"Y"can be M, M1, MH, M1 H, M4, M41-1, or P; "ZZ"can be 20 or 24;
I and "A"can be F,T, U, UH, or TH
t
Recom modules with 35 and 40 mm frames
i
Recom RCM-xxx-6yy
Where"yy'can be MA, MB, ME or MF
REC modules with 30, 38 and 45 mm frames
RECxxxYYZZ
REC Solar Where"YY"can be AN M, NP, NP2, PE, PE72,TP,TP2,TP2M,TP2SM,TP2S,
TP3M or TP4; and "ZZ"can be blank, Black, BLK, BLK2, SLV, 72 or Pure
ReneSola modules with 35, 40 and 50 mm frames
AAxxxY-ZZ
Renesola Where"AA"can be SPM(SLP)or JC; "Y"can be blank, F, M or S; and "ZZ"
can be blank,Ab,Ab-b,Abh,Abh-b,Abv,Abv-b, Bb, Bb-b, Bbh, Bbh-b, Bbv,
Bbv-b, Db, Db-b, or 24/BbWU
Renogy Modules with 40 and 50 mm frames
Renogy RNG-xxxY
Where"xxx"is the module power rating; and"Y"can be D or P
Risen Modules with 35 and 40 mm frames
Risen RSMyy-6-xxxZZ
Where"yy'can be 60, 72, 120, 132 or 144; and"ZZ"can be M or P
S-Energy modules with 35 and 40mm frames
SABB-CCYYY-xxxZ
S-Energy Where"A"can be C, L or N; "BB"can be blank, 20,40 or 45;"CC"can be
blank, 60 or 72;"YYY" can be blank, MAE, MAI, MBE, MBI, MCE or MCI; and
"Z"can be V, M-10, P-10 or P-15
SEG Solar modules with 35 and 40 mm frames
SEG-aYY-xxx-ZZ
SEG Solar Where"a"can be blank, 6 or B;"YY"can be blank, MA, MB, PA, or PB; and
"ZZ"can be blank, BB, BG, BW, HV, WB,WW, BMB, BMA-HV, BMA-TB, BMB-
HV, BMB-TB, BMD-HV
Seraphim modules with 35,40 and 50 mm frames
SRP-xxx-YYY-ZZ
Seraphim USA
Where"xxx" is the module power rating; and "YYY"can be 6MA, 6MB, 6PA,
6PB, BMD, 6QA-XX-XX, and 6QB-XX-XX; ZZ is blank, BB or HV
.�.
INSTALLATION GUIDE
EcoFasten
APPROVEDFoi- InstaLlers. By Installers.
MANUFACTURER LIST OF UL 2703 •
Sharp modules with 35 and 40 mm frames
Sharp ( NUYYxxx
(Where"YY"can be SA or SC
Silfab Modules with 35 and 38 mm frames
Silfab SYY-Z-xxxAb
Where"YY"can be IL, SA, LA, SG or LG; "Z"can be blank, M, P, or X;"A"can
be blank, B, H, M, N; and"b"can be A, C, G, K, L, N,T, UorX
Solaria modules with 35 and 40 mm frames
Solaria PowerXT-xxxY-ZZ
Where"Y"can be R or C; and"ZZ"can be AC, BD, BX, BY, PD, PL, PM, PM-AC,
PX, PZ, WX or WZ
Solarcity modules with 40 mm frames
Solarcity s
(Tesla) cxxxYY
Where"YY"can be blank, 131 or B2
SolarTech modules with 40 and 42 mm frames
SolarTech AAA-xxxYY
Where"AAA"can be PERCB-B, PERCB-W, HJTB-B, HJTB-W or STU; "YY"can be
blank, PERC or HJT
SolarWorld Sunmodule Plus, Protect, Bisun,XL, Bisun XL, may be followed
SolarWorld AG by mono, poly, duo, black, bk, or clear; modules with 31, 33 or 46 mm
frames
SW-xxx
SolarWorld Sunmodule Plus, Protect, Bisun, XL, Bisun XL, may be followed
SolarWorld by mono, poly, duo, black, bk, or clear; modules with 33 mm frames
Americas
SWA-xxx
Sonali Sonali Modules with 40 mm frames
SSxxx
i
Ston Stion Thin film modules with 35 mm frames I
STO-xxx or STO-xxxA
SunEdison Modules with 35,40 &50 mm frames
SE-YxxxZABCDE
SunEdison Where"Y"can be B, F, H, P, R, or Z; "Z"can be 0 or 4;"A"can be B, C, D, E, H,
I,J, K, L, M, or N ; "B"can beBorW; "C"can beAorQ"D"can be 3, 7, 8, or 9;
and "E"can be 0, 1 or 2
Suniva modules with 35, 38, 40,46, and 50 mm frames
O PTxxx-AA-B-YYY-Z
Suniva MVXxxx-AA-B-YYY-Z
Where"AA"is either 60 or 72; "B"is either 4 or 5; "YYY" is either
100,101,700,1 B0, or 1 B1; and "Z" is blank or B
A
GUIDEINSTALLATION o F a s t e n
For Installers. By Installers.
MANUFACTURER LIST OF UL 2703 APPROVED MODULES
Sunpower standard (G3 or G4)or InvisiMount(G5)35,40 and 46 mm
frames
SPR-Zb-xxx-YY
Sunpower Where"Z" is either A, E, P, M or X; "b"can be blank, 17, 18, 19, 20, 21, or 22;
and "YY"can be blank, BLK, COM, C-AC, D-AC, E-AC, BLK-E-AC, G-AC, BLK-C-
AC, or BLK-D-AC
Sunspark modules with 40 mm frames
Sunspark SYY-xxxZ-A
Where"YY"can be MX or ST; and "Z"can be M, MB, M3, M313, P or W; and
"A"can be 60 or 72
Suntech Modules with 35,40 and 50mm frames
Suntech STPxxxy-zz/aa
Where"y"is blank or S; and "z"can be 20, 24,A60 or A721-1; and"aa"can be
Vd,Vem,Vfw,Vfh, Wdb, Wde,Wd, or Wfhb
Talesun modules with 35 and 40mm frames
TP6yZZaaxxx-b
Talesun Where"y"can be blank, F, H, or L;"ZZ"can be 60 or 72;"aa"can be M, M(H),
or P; and "b"can be blank, B, T, or(H)
Tesla modules with 40 mm frames
Tesla TxxxY
Where"Y"can be H or S
Trina Modules with 30, 35, 40 and 46mm frames
TSM-xxxYYZZ
Where"YY"can be DD05, DD06, DD14, DE09, DE14, DE06X, DE15, DE15V,
Trina DEG15, PA05, PC05, PD05, PD06, PA14, PC14, PD1 4, PE14, or PE15; and "ZZ"
can be blank, (II), .05, .05(11), .08, .10, .18, .OBD, .18D, 0.82_002_00S,00S, 055,
08S,A,A.05,A.08, A.10,A.18,A(II),A.05(11), A.08(II),A.082(II),A.10(11), A.18(II),
H, H(II), H.05(II), H.08(II), HC.20(11), HC.20(II), M, M(II), M.05(11), MC.20(II)
URE modules with 35 mm frames
URE DyZxxxaa
Where"D"can be D or F,"y"can be A, 6 or 7;"Z"can be K or M; and"aa"can
be H3A, H4A, HBA, E7G-BB, E8G or E8G-BB
Vikram solar modules with 40 mm frames
Vikram VSyy.ZZ.AAA.bb
Where"yy'can be M, P, MBB, MH, MS, MHBB, or PBB; "ZZ"can be 60 or 72;
"AAA" is the module power rating; and "bb"can be 03, 04 or 05
------------------ i
INSTALLATION GUIDE ..� Eco Fasten
For Installers. By Installers.
MANUFACTURER LIST OF 2703 APPROVED M •
VSUN modules with 30, 35 and 40 mm frames
VSUN VSUNxxx-YYz-aa .
Where"YY"can be 60, 72, 108, 120, or 144;"z"can be M, P, MH, PH, or BMH;
and "aa"can be blank, BB or BW
j Waaree modules with 40mm frames
Waaree WSyy-xxx
where"yy'can be blank or M
Winaico modules with 35 and 40 mm frames
Winaico Wsy-xxxZa
Where"y"can be either P or T;"Z"can be either M, P, or MX; and"a"can be
blank or 6
Yingli modules with 35 and 40 mm frames
jYingli YLxxxZ-yy
Where"Z"can be D or P;"y)('can be 29b, 30b, 34d, 35b, 36b or 40d
ZN Shine modules with 35mm frames
ZN Shine ZXMY-AAA-xxx/M
Where"Y"can be 6 or 7, "AAA"can be 72, NH120, NH144 or NHDB144
I
INSTALLATION GUIOE
EcoFasten
Foi Installers. By InstaLiers.
CLAMP PART NUMBERS
END CLAMPS
Frame Thickness Article Number
30 mm 2099016
32 mm 2099017
35 mm 2099018
38 mm 2099019
40 rnm 2099020
45 m m 2099021
MID CLAMPS
Frame Thickness Article Number
30-40 mm 2099022
40-50 mm 2099023
INSTALLER RESPONSIBILITIES
Periodic re-inspection of components shall be performed to verify that there is no corrosion
detrimental to system strength and electrical conductivity, no loose bolts, and/or other
variables that could compromise array safety.Any corroded or damaged components shall be
immediately replaced.
•