Report COMcheck Software Version 4.1.5.0
SITE COPY
Mechanical Compliance Certificate ECEIVED
� a� JUN 11 2021
L S ‘'`.1 CITY OF TIGARD
Project Information Si 1 BUILDING DIVISION
Energy Code: 2018 IECC ^ 1 t' Ji• IL
Project Title: Peloton at Washington Square
Location: Portland,Oregon 4t. tj
Climate Zone: 4c -
Project Type: New Construction
Construction Site: Owner/Agent: Designer/Contractor:
9355 S.W. Washington Square Road One Peloton Thorson Baker and Associates
Portland, OR 97223 125 W. 25th St. 3030 W Streetsboro Rd.
New York, NY 10001 Richfield, OH 44286
Additional Efficiency Package(s)
High efficiency HVAC.Systems that do not meet the performance requirement will be identified in the mechanical requirements checklist
report.
Mechanical Systems List
Quantity System Type&Description
1 FCU-4(Single Zone):
Heating: 1 each-Duct Furnace,Electric,Capacity=33 kBtu/h
No minimum efficiency requirement applies
Cooling: 1 each-Hydronic Coil,Capacity=59 kBtu/h,Air Economizer
No minimum efficiency requirement applies
Fan System: FAN SYSTEM 1 --Compliance(Motor nameplate HP method):Passes
Fans:
FAN 1 Supply,Constant Volume, 1600 CFM,0.8 motor nameplate hp,0.0 fan efficiency grade
Mechanical Compliance Statement
Compliance Statement: The proposed mechanical design represented in this document is consistent with the building plans,
specifications, and other calculations submitted with this permit application.The proposed mechanical systems have been
designed to meet the 2018 IECC requirements in COMcheck Version 4.1.5.0 and to comply with any applicable mandatory
requirements listed in the Inspection Checklist.
Nathaniel Kobb 6/9/2021
Name -Title Signature Date
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 1 of 11
COMcheck.cck
COMcheck Software Version 4.1.5.0
irl‘ftfil Inspection Checklist
I Energy Code: 2018 IECC
Requirements: 100.0% were addressed directly in the COMcheck software
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Section
# Plan Review Complies? Comments/Assumptions
&Req.ID
C103.2 Plans, specifications, and/or ❑Complies Requirement will be met.
[PR2)1 calculations provide all information ODoes Not
!with which compliance can be
determined for the mechanical ❑Not Observable
systems and equipment and ONot Applicable
document where exceptions to the
standard are claimed. Load
calculations per acceptable
engineering standards and
handbooks.
C406 Plans, specifications, and/or ❑Complies Requirement will be met.
[PR9]1 calculations provide all information ❑Does Not
with which compliance can be
determined for the additional energy ONot Observable
efficiency package options. ONot Applicable
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 2 of 11
COMcheck.cck
Section
# Footing / Foundation Inspection Complies? Comments/Assumptions
& Re .lD
C403.12.2 Snow/ice melting system and freeze ❑Complies mm Exception: Requirement does not apply.
protection systems have sensors and ElDoes Not
C403.12.3 controls configured to limit service for
[FO9)3 pavement temperature and outdoor :Not Observable
temperature. future connection to ❑Not Applicable
controls,
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 3 of 11
COMcheck.cck
Section I
# i Plumbing Rough-In Inspection Complies? Comments/Assumptions
& Req.ID
C404.5, Heated water supply piping conforms ❑Complies Requirement will be met.
C404.5.1, to pipe length and volume ❑Does Not
C404.5.2 requirements. Refer to section details. ONot Observable
[PL6]3
ONot Applicable
C404.6.3 Pumps that circulate water between a ❑Complies Exception: Requirement does not apply.
[PL7]3 heater and storage tank have controls ❑Does Not
that limit operation from startup to
<= 5 minutes after end of heating ONot Observable
cycle. .❑Not Applicable
C404.7 Demand recirculation water systems ❑Complies Requirement will be met.
[PL8]3 have controls that start the pump '❑Does Not
upon receiving a signal from the
action of a user of a fixture or ❑Not Observable
appliance and limits the temperature ONot Applicable
of the water entering the cold-water
piping to 104°F.
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 4 of 11
COMcheck.cck
Section
Mechanical Rough-In Inspection Complies? Comments/Assumptions
& Req.ID
C402.2.6 Thermally ineffective panel surfaces of❑Complies Exception: Requirement does not apply.
[ME41]3 sensible heating panels have ODoes Not
insulation >= R-3.5. ONot Observable
ONot Applicable
C403.11.3 HVAC piping insulation insulated in ❑Complies 'Requirement will be met.
[ME61]2 accordance with Table C403.11.3. IDDoes Not
Insulation exposed to weather is
protected from damage and is ❑Not Observable
provided with shielding from solar ONot Applicable
radiation.
C403.8.4 Motors for fans that are not less than ❑Complies Requirement will be met.
[ME142]z 1/12 hp and less than 1 hp are ODoes Not
electronically commutated motors or
have a minimum motor efficiency of ONot Observable
70 percent.These motors have the ONot Applicable '.
means to adjust motor speed.
C403.8.5 Each DX cooling system > 65 kBtu ❑Complies 'Exception: Requirement does not apply.
[ME143]2 and chiller water/evaporative cooling ❑Does Not
'system with fans > 1/4 hp are :Not Observable
designed to vary the indoor fan airflow
as a function of load and comply with ONot Applicable
detailed requirements of this section.
C403.12.1 Systems that heat outside the building OComplies Exception: Requirement does not apply.
[ME71]? envelope are radiant heat systems ❑Does Not
controlled by an occupancy sensing
device or timer switch. Not Observable
ONot Applicable
C403.2.3 HVAC equipment efficiency verified. ❑Complies 'See the Mechanical Systems list for values.
[ME5512 ODoes Not
O Not Observable
O Not Applicable
C403.5.5 Fault detection and diagnostics ❑Complies Exception: Requirement does not apply.
[ME113]z installed with air-cooled unitary DX ODoes Not
units having economizers.
ONot Observable'
O Not Applicable
C403.2.2 Natural or mechanical ventilation is ❑Complies Requirement will be met.
[ME59]1 provided in accordance with ODoes Not
International Mechanical Code
Chapter 4. Mechanical ventilation has ,ONot Observable
capability to reduce outdoor air supply'ONot Applicable
to minimum per IMC Chapter 4.
C403.7.1 Demand control ventilation provided ❑Complies Exception: Requirement does not apply.
[ME59]1 for spaces >500 ft2 and >25 ❑Does Not
people/1000 ft2 occupant density and
served by systems with air side ONot Observable
economizer, auto modulating outside ONot Applicable
air damper control, or design airflow
>3,000 cfm.
C403.7.2 Enclosed parking garage ventilation ❑Complies Exception: Requirement does not apply.
[ME115]3 has automatic contaminant detection ❑Does Not
and capacity to stage or modulate
fans to 50%or less of design capacity. ONot Observable
❑Not Applicable
C403.7.6 HVAC systems serving guestrooms in ❑Complies Exception: Requirement does not apply.
[ME141]3 Group R-1 buildings with > 50 ODoes Not
guestrooms: Each guestroom is
provided with controls that ['Not Observable
automatically manage temperature ONot Applicable
setpoint and ventilation (see sections
C403.7.6.1 and C403.7.6.2).
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 5 of 11
COMcheck.cck
Section
# Mechanical Rough-In Inspection Complies? Comments/Assumptions
& Req.ID
C403.7.4 Exhaust air energy recovery on ❑Complies Exception: Requirement does not apply.
[ME57]1 systems meeting Table C403.7.4(1) ODoes Not
and C403.7.4(2).
ONot Observable
ONot Applicable
C403.7.5 Kitchen exhaust systems comply with ❑Complies Exception: Requirement does not apply.
[ME116]3 replacement air and conditioned ODoes Not
supply air limitations, and satisfy hood
rating requirements and maximum ONot Observable
exhaust rate criteria. ONot Applicable
C403.11.1 HVAC ducts and plenums insulated in ❑Complies Exception: Requirement does not apply.
accordance with C403.11.1 and ODoes Not
C403.11.2 constructed in accordance with
[ME60]2 C403.11.2,verification may need to ❑Not Observable
occur during Foundation Inspection. ONot Applicable
C403.5, Air economizers provided where :Complies Exception: Requirement does not apply.
C403.5.1, required, meet the requirements for ❑Does Not
C403.5.2 design capacity, control signal,
[ME62j1 ventilation controls, high-limit shut-off, ONot Observable
integrated economizer control, and ONot Applicable
provide a means to relieve excess
outside air during operation.
C403.5.3. Air economizers automatically reduce ❑Complies Exception: Requirement does not apply.
3 outdoor air intake to the design ODoes Not
[ME124]1 minimum outdoor air quantity when
outdoor air intake will not reduce Not Observable
cooling energy usage. See Table ❑Not Applicable
C403.5.3.3 for applicable device types
and climate zones.
C403.5.3. System capable of relieving excess '❑Complies Exception: Requirement does not apply.
4 outdoor air during air economizer ODoes Not
(ME125]1 operation to prevent overpressurizing
the building.The relief air outlet ONot Observable
located to avoid recirculation into the ONot Applicable
building.
C403.5.3. Return, exhaust/relief and outdoor air ❑Complies Exception: Requirement does not apply.
5 dampers used in economizers have ODoes Not
[ME126j1 motorized dampers that automatically
shut when not in use and meet ONot Observable
maximum leakage rates. Reference ONot Applicable
section C403.7.7 for details.
C403.4.3. '.Three-pipe hydronic systems using a ❑Complies Requirement will be met.
1 common return for hot and chilled ODoes Not
[ME50]2 water are not used.
ONot Observable
ONot Applicable
C403.4.5 Chilled water plants with multiple DComplies Requirement will be met.
[ME26]3 chillers have capability to reduce flow ODoes Not
automatically through the chiller plant
when a chiller is shut down. Boiler Not Observable',
plants with multiple boilers have the ONot Applicable
capability to reduce flow automatically
through the boiler plant when a boiler
is shut down.
C403.4.1. Heating for vestibules and air curtains ❑Complies Exception: Requirement does not apply.
4 with integral heating include ODoes Not
[ME63]2 automatic controls that shut off the
heating system when outdoor air ONot Observable
temperatures >45F.Vestibule ONot Applicable
heating and cooling systems
controlled by a thermostat in the
vestibule with heating setpoint <=
60F and cooling setpoint >= 80F.
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 6 of 11
COMcheck.cck
Section
# Mechanical Rough-In Inspection Complies? Comments/Assumptions
& Req.ID
C403.9.5 Condenser heat recovery system that ❑Complies Requirement will be met.
[ME31]3 can heat water to 85°F or provide ['Does Not
60%of peak heat rejection is installed
for preheating of service hot water. ONot Observable
ONot Applicable
C408.2.2. Air outlets and zone terminal devices '❑Complies Requirement will be met.
1 have means for air balancing. ❑Does Not
[ME53]3 ONot Observable
ONot Applicable
C408.2.2. HVAC hydronic heating and cooling ❑Complies Requirement will be met.
2 coils have means to balance and have ODoes Not
[ME54]3 pressure test connections.
ONot Observable
ONot Applicable
C403.5, 'Refrigerated display cases, walk-in ❑Complies Exception: Requirement does not apply.
C403.5.1, coolers or walk-in freezers served by ODoes Not
C403.5.2 remote compressors and remote
[ME123]3 condensers not located in a ONot Observable
condensing unit, have fan-powered ONot Applicable
condensers that comply with Sections
C403.5.1 and refrigeration compressor
systems that comply with C403.5.2..
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 7 of 11
COMcheck.cck
Section
# Rough-In Electrical Inspection Complies? Comments/Assumptions
& Req.ID
C405.6 Low-voltage dry-type distribution ❑Complies Requirement will be met.
[EL26]2 electric transformers meet the ❑Does Not
minimum efficiency requirements of
Table C405.6. ONot Observable
ONot Applicable
C405.7 Electric motors meet the minimum ❑Complies Requirement will be met.
[EL27]2 efficiency requirements of Tables ❑Does Not
C405.7(1)through C405.7(4).
Efficiency verified through certification'❑Not Observable'
under an approved certification ONot Applicable
program or the equipment efficiency
ratings shall be provided by motor
manufacturer(where certification
programs do not exist).
C405.8.2, Escalators and moving walks comply ❑Complies Exception: Requirement does not apply.
C405.8.2. !with ASME A17.1/CSA B44 and have ❑Does Not
1 automatic controls configured to
[EL28]2 reduce speed to the minimum :Not Observable
permitted speed in accordance with ONot Applicable
ASME A17.1/CSA B44 or applicable
local code when not conveying
passengers.
C405.9 Total voltage drop across the '❑Complies Requirement will be met.
[EL29]2 combination of feeders and branch ODoes Not
circuits <= 5%.
:Not Observable
ONot Applicable
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 8 of 11
COMcheck.cck
Section
Final Inspection Complies? Comments/Assumptions
&Req.ID
C303.3, Furnished O&M manuals for HVAC DComplies Requirement will be met.
C408.2.5. systems within 90 days of system ODoes Not
3 acceptance.
[Fie ❑Not Observable
ONot Applicable
C403.2.2 HVAC systems and equipment DComplies :Requirement will be met.
[FI27]3 capacity does not exceed calculated Does Not
loads.
ONot Observable!
O Not Applicable
C403.2.4. Heating and cooling to each zone is DComplies 'Requirement will be met.
1 controlled by a thermostat control. ODoes Not
[F147]3 Minimum one humidity control device
per installed ONot Observable
humidification/dehumidification ONot Applicable
system.
C403.4.1. Thermostatic controls have a 5 °F ❑Complies Requirement will be met.
2 deadband. ❑Does Not
[F138]3 ONot Observable'
ONot Applicable
C403.2.4. Temperature controls have setpoint DComplies Requirement will be met.
1.3 overlap restrictions. ❑Does Not
[F120]3 ONot Observable
ONot Applicable
C403.2.4. 'Each zone equipped with setback OComplies Requirement will be met.
2 controls using automatic time clock or ODoes Not
[F139]3 programmable control system.
ONot Observable
ONot Applicable
C403.2.4. ':Automatic Controls: Setback to 55°F DComplies Requirement will be met.
2.1, (heat)and 85°F (cool); 7-day clock, 2- ODoes Not
C403.2.4. hour occupant override, 10-hour
2.2 backup :Not Observable
[F140]3 ONot Applicable
C403.2.4. Systems include optimum start '❑Complies Requirement will be met.
2.3 controls. ODoes Not
[F141]3 ONot Observable
O Not Applicable
C408.1.1 'Building operations and maintenance DComplies Requirement will be met.
[F157]1 documents will be provided to the ODoes Not
owner. Documents will cover
manufacturers' information, ONot Observable
specifications, programming ONot Applicable
procedures and means of illustrating
to owner how building, equipment and
systems are intended to be installed,
maintained, and operated.
C408.2.1 Commissioning plan developed by DComplies Requirement will be met.
[FI28]1 registered design professional or ODoes Not
approved agency.
:Not Observable
ONot Applicable
C408.2.3. HVAC equipment has been tested to DComplies Requirement will be met.
1 ensure proper operation. ODoes Not
[FI31]1 :Not Observable
O Not Applicable
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 9 of 11
COMcheck.cck
Section
Final Inspection Complies? Comments/Assumptions
& Req.ID
C408.2.3. HVAC control systems have been _❑Complies Requirement will be met.
2 tested to ensure proper operation, ODoes Not
[FI10]1 calibration and adjustment of controls.
❑Not Observable
❑Not Applicable
C408.2.3. Economizers have been tested to ❑Complies Requirement will be met.
3 ensure proper operation. ODoes Not
[F132]1 ONot Observable
❑Not Applicable
C408.2.4 Preliminary commissioning report DComplies Requirement will be met.
[F129]1 completed and certified by registered ODoes Not
design professional or approved
agency. DNot Observable
❑Not Applicable
C408.2.5. Furnished HVAC as-built drawings ❑Complies Requirement will be met.
1 submitted within 90 days of system ❑Does Not
[F17]3 acceptance.
[Not Observable
❑Not Applicable
C408.2.5. An air and/or hydronic system ;❑Complies Requirement will be met.
3 balancing report is provided for HVAC ODoes Not
[FI43]1 systems. :❑Not Observable
❑Not Applicable
C408.2.5. Final commissioning report due to ❑Complies Requirement will be met.
4 building owner within 90 days of ODoes Not
[F130]1 receipt of certificate of occupancy.
❑Not Observable
❑Not Applicable
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 10 of 11
COMcheck.cck
Project Title: Peloton at Washington Square Report date: 05/24/21
Data filename: \\tbs-projects05\2021\2021-0237\Engineering\_Energy-Calcs\2021-0237 Mechanical Page 11 of 11
COMcheck.cck