Permit Support Document 5. Please clarify how many fuel lines will be installed and what appliances they will serve. The
bottom of the machinal permit application was not filled out. I am counting 5 but need to
confirm.
Fuel piping=4
2—Fireplace
1—Range
1—Furnace
Water Heater will be electric.
6. Please advise which room is to be the 4th bedroom? Building permit application has 4
marked but the plan shows 3+Den+Bonus.
Bedrooms=4,+ Den
7. The low profile 4/12 pitch roof does not allow for enough room at the inside face of the
exterior wall at the top plan to meet the minimum R-21 insulation requirement. How do
you intent to meet this requirement. See Table N1101.1(1) Note f.
Please see attached typical detail on updated house plans.
Please let me know if you have any questions.
Thank you,
Allyson Armstrong
503-718-8137
Agnes Lindor
From: Agnes Lindor
Sent: Wednesday, December 15, 2021 2:32 PM
To: valh@chaddavisconstruction.com
Cc: Trent Brickey; #Building Permit Technicians
Subject: Bull Mountain Summit Lots 1-4 and 7-11
Attachments: SUB2020-00002 Bull Mountain Conditions 12-15-2021.pdf
Good afternoon-
These permits have been placed in approved but not release status until the plat has been recorded and the remaining
conditions required prior to commencing site work have been met (condition 28). Please see attached condition report.
Agnes Lindor I Associate Planner
City of Tigard I Community Development
13125 SW Hall Boulevard
Tigard, Oregon 97223
Phone: 503.718.2429
Email:AgnesL@tigard-or.gov