Plans (3) - EODESIGN: FIELD REPORT
Page 1 of 1
GDI Project: Polygon 1 13-05 Prepared By: Joey Fischer
Project Name: Roshak Ridge 9/2/21
Location: SW Bull Mountain Road and SW Roy Report#: 203
Rogers Road,Tigard
Arrival: 1300 Departure: 1320
Weather: Sunny, 70s Permit#: i TBA
Site Visit Requested By: Rob(Taylor Morrison) Met With (on site): 1 Rob (Via Phone)
Purpose: Observe Lot 1 56 Subgrade
...........................
Outstanding Issues:
Upon arrival, I was informed that onsite earthwork crew had prepared subgrade for the building within lot 1 56.
Subgrade consisted of native brown silt. Using a Y2" diameter steel foundation rod, I probed the subgrade.
Resistance to penetration indicated stiff to very stiff material.
Based on observations and probing, it is our opinion that lot 156 subgrade observed today as indicated on the
attached site plan, has been prepared in general accordance with our geotechnical recommendations.
Distribution:
Attachments: Site Plan (1)
Reviewed by:
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering or environmental services.We rely on the contractor to comply with the plans and
specifications throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the contractor,the contractor's employees
or agents. Our firm is not responsible for site safety. This field report is a DRAFT representation of our field observations,testing,and preliminary recommendations.The report can only be
considered final upon review of the GeoDesign project manager,as indicated by initials in the"Reviewed By"section.
6) .
Signature: ,,