01/21/1960 - Minutes SPRCIAL MEETING
TIGARD WATER DISTRICT
TIGARD OREGON
� - January 21, 1960
Present, A.J.Xhavez president, A,G.Ames, Curtis Tigard, C.F.
Nicoll, E.C. Phillips Commissioners, J.P.Lohrenz Supt, E.W.
Carter Eng. and six bidders.
The president called the meeting to order at 8.30 P.M. Oclock,
The meeting was held in the offices of the District at 8841 SW.
Commercial Street, Tigard, Oregon
The purpose of the special meeting was to open bids and accept
one for the construction of the new tank at Well # 3.
The Engineer Elden W. Carter opened and read the bids as sub-
mitted as follows:-
1 Riverside Construction Co.
P.O.Box 3853, Portland 8, Oregon
Their bid was $35,242.50.
2 Charles S. Camplan
2035 S.W. 58th. Ave. Portland, Oregon
Their bid was $32,772.50
3 L.B. Read
2607 S.W. Sunset Blvd. Portland 10, Oregon
Their bid was $32,445.50
4 Bickford Construction Co.
823 S.E. 28th. Portland 14, Oregon.
Their bid was $31,352.00.
5 Schrader Construction Co.
3621. S.E. 52nd. Ave. Portland, Oregon
Their bid was $31,980.00
6 Zuber Bro.
3600 S.E. 28th Ave. Portland Oregon
Their bid was 03,495.00
Curtis Tigard moved and A.G.Ames seconded that the bid of
Dickfor Construction Co. bid # 4 be accepted, after the bid has
been approved by the Engineer E.W. Carter. The motion carried.
PresidentAmaik_ Adi ! , Sec
A.G. Ames moved and E.C. Phillips seconded that the
meeting adjourn. The motion carried.
President q4 d Secretary�����