Correspondence Branden Taggart
From: Branden Taggart
Sent: Monday,January 11, 2021 10:39 AM
To: Yevgeniy Zakharov
Cc: Dianna Ornelas
Subject: Permit for Jeremy Audritsh: MST2020-00320 - 12555 SW Pathfinder Ct.
Attachments: Invoice.pdf ._—
Hello Yevgeniy,
The Building permit for Jeremy Audritsh is ready to issue now. The balance due is$711.27, and I have attached an
invoice above for you to reference. The permit fees can be paid online through our
website: https://aca.accela.com/tigard/Default.aspx. From there, click on the Building tab, enter the permit number
(MST2020-00320) in the Record Number field, and click Search. Once paid, please notify us at
TigardBuildingPermits(«tigard-or.gov, and we will place this permit and the approved site copy set of plans in our open
Permit Center conference room for you to pick up between the hours of 8:00 a.m. and 5:00 p.m., Monday through
Thursday. We are closed on Fridays. No appointment is necessary to pick up.
Thank you,
Branden Taggart
■ City of Tigard
Senior Permit Technician
Community Development
13125 SW Hall Blvd
Tigard, OR 97223
(503)718-2449
brandent@tigard-or.gov
1
•
Branden Taggart
From: #Building Permit Technicians
Sent: Monday, November 16, 2020 6:00 PM
To: Yevgeniy Zakharov
Cc: Dianna Ornelas
Subject: RE: IIBUP_RESPermitApp - 12555 SW Pathfinder Ct.
Attachments: BUP_RES_PermitApp.pdf
Hello Yevgeniy,
We received (1) additional set of plans, but we are missing the (3) copies of the site plan. After numerous separate
submittals,we have yet to receive all of the required materials. Since you submittal is currently incomplete, I will be
placing it in our Permit Center conference room for you to pick up and return once it is complete. The applicant is
responsible for ensuring permit submittals are complete. We will not accept incomplete application submittal packets,
or application materials submitted separately on separate dates or times. Per my previous email,the deck submittal
requirements can be viewed through our Tigard Deck Guide: https://www.tigard-
or.gov/city hall/departments/CommunityDevelopment/Tigard Deck Guide.pdf. Additionally, I have attached our
Residential Building Permit Application for you to reference the required plan review items.
When complete,you may mail or delivered this submittal in person to our Permit Center lobby drop box, between the
hours of 8:00 a.m. and 5:00 p.m., Monday through Thursday. We are closed on Fridays. No appointment is necessary to
deliver this submittal in person.
After this submittal is accepted, and the permit is created, we will notify you when the plan review fees can be paid
online with a credit card or check. As previously stated, our current permit processing time is 4-8 weeks. We will
contact you when the permit is ready to issue. It is not necessary to contact us regarding the status of your permit as
this will further delay the process. We appreciate your patience. Please let me know if you have questions.
Thanks,
Branden Taggart
City of Tigard
t Senior Permit Technician
Community Development
13125 SW Flail Blvd
Tigard, OR 97223
(503)718-2449
brandent@tigard-or.gov
From:#Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>
Sent:Wednesday, November 4, 2020 7:18 AM
To:Yevgeniy Zakharov<craft.remodel@gmail.com>
Cc: Dianna Ornelas<Dianna@tigard-or.gov>; Edgardo Maldonado <edgardom@tigard-or.gov>
Subject: RE: IIBUP_RESPermitApp- 12555 SW Pathfinder Ct.
Yevgeniy,
Per my email,we will need to receive (1) additional set of plans and (3) copies of a site plan.
1
•
Thanks,
Branden Taggart
11Ba City of Tigard
:.t,P, Senior Permit Technician
Community Development
13125 SW Hall Blvd
Tigard, OR 97223
(503)718-2449
brandent@tigard-or.gov
From:Yevgeniy Zakharov<craft.remodel@gmail.com>
Sent:Wednesday, November 4, 2020 4:02 AM
To:#Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>
Cc: Dianna Ornelas<Dianna(«tigard-or.gov>; Edgardo Maldonado <edgardom@tigard-or.gov>
Subject: Re: IIBUP_RESPermitApp - 12555 SW Pathfinder Ct.
Caution!This message was sent from outside your organization.
So you just need site plan and one more copy?
Thank you for contacting
Yevgeniy Zakharov
On Nov 4, 2020, at 7:01 AM,Yevgeniy Zakharov<craft.remodel@gmail.com>wrote:
This just small deck 8 weeks to review
Thank you for contacting
Yevgeniy Zakharov
On Nov 3, 2020, at 8:57 PM, #Building Permit Technicians
<TigardBuildingPermits@tigard-or.gov>wrote:
Hello Yevgeniy,
I located the plans that you mailed to us. We are still missing(1) additional of plans and
(3) copies of a site plan. In order for us to begin plan review,we will need to receive a
complete submittal. Please refer to my previous email with the link to all of the deck
permit requirements. Also, I have attached the Site Plan Guide above to assist you with
the site plan requirements.
Once we receive a complete submittal, plan review will take approximately 4-8 weeks.
Thank you,
2
<image001.jpg>
From:Yevgeniy Zakharov<craft.remodel@gmail.com>
Sent: Monday, November 2, 2020 9:09 AM
To:#Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>
Subject: Re: IIBUP_RESPermitApp- 12555 SW Pathfinder Ct.
You did revviced plans you sent me letter
Saying you got the plans but no application I sent the application few days later
Thank you for contacting
Yevgeniy Zakharov
On Nov 2, 2020, at 11:56 AM,#Building Permit Technicians
<TigardBuildingPermits@tigard-or.gov>wrote:
Hello Yevgeniy,
Thank you for the Building Permit Application. We apologize for the
delayed response. We have had limited staff recently, and we are doing
our best to respond to emails as quickly as possible. Regarding your
submittal, it appears we have not received deck plans.
You can view the deck submittal requirements through our Tigard Deck
Guide: https://www.tigard-
or.gov/citv hall/departments/CommunitvDevelopment/Tigard Deck G
uide.pdf
When you are ready to submit for this Building permit,you are welcome
to deliver your submittal (completed application and plans)to our drop
box, located in the lobby of the Permit Center, between the hours of
8:00 a.m. and 5:00 p.m., Monday through Thursday (see attached aerial
shot for the location). We are closed on Fridays. No appointment is
necessary to deliver your submittal. Additionally, if this submittal can
be printed on 8.5" x 11" or 11" x 17" pages, and there are less than fifty
pages total,you may submit your plans by email to
TigardBuildingPermits@tigard-or.gov.
Please note that our current permit processing time is 4-8 weeks. We
will contact you for payment of the plan review fees after the permit
has been created. The plan review fees will need to be paid online with
a credit card or check. Please note that it is not necessary to contact us
regarding the status of your permit as this will further delay the
process. We appreciate your patience. Please let me know if you have
additional questions.
Thank you,
3
<image001.jpg>
From: Yevgeniy Zakharov<craft.remodel@gmail.com>
Sent:Tuesday, October 13, 2020 3:40 PM
To:#Building Permit Technicians<TigardBuildingPermits@tigard-
or.gov>
Subject: IIBUP_RESPermitApp
The plans been mailed already you should have them
This document was signed using Adobe Fill &Sign.
Get the app for iOS or Android .
Want to send documents for signature and track responses? Learn more
about Adobe Sign.
Thank you for contacting
Yevgeniy Zakharov
DISCLAIMER: E-mails sent or received by City of Tigard employees are
subject to public record laws. If requested, e-mail may be disclosed to
another party unless exempt from disclosure under Oregon Public
Records Law. E-mails are retained by the City of Tigard in compliance
with the Oregon Administrative Rules"City General Records Retention
Schedule."
<BUP_RESPermitApp.pdf>
<SitePlanlnfo_100113.pdf>
4