Correspondence (4) Pence Construction, LLC
5400 Meadows Road Suite 400
Lake Oswego, Oregon 97035 Transmittal., „,F C ¢y...,
CONSTRUCTION 503/399-7223, FAX / No 0576 I ..s
AUG 1 0 2020
CITY`
SUILDiNV
PROJECT: Tigard High School Modernization Project DATE: Aug 07,2020
To: Bassetti Architects P.S.,P.C. RE: THS-Tig Stair 04,06,07,08,09,12,13 Shop Drawings-R&R
721 NW 9th Avenue,Suite 350
Portland OR 97209
ATTN: Greg Vohs JOB: 317-045
WE ARE SENDING: SUBMITTED FOR: ACTION TAKEN:
✓ Shop Drawings ✓ Approval Approved as Submitted
Letter Your Use Approved as Noted
Prints As Requested Returned After Loan
Change Order Review and Comment Resubmit
Plans Submit
Samples SENT VIA: Returned
Specifications Attached I Separate Cover Returned for Corrections
Other: Due
✓ Submittal: Other:
Line Item Package Code Rev. QTY Date Description Status
1 Attachment 99511333 0 Aug 07,2020 TIG-814-Submittal#12.4 S1
Stairs STAMPED
REMARKS THS-Tig Stair 04,06,07,08,09,12,13 Shop Drawings-R&R
REVIEWED
THIS REVIEW IS NOT AN APPROVAL OF ANY
DEVIATION FROM THE REQUIREMENTS OF THE
cc: CONTRACT DOCUMENTS.
Pence Construction,LLC,Carl Schrank DATE:&108/07120) APPROVED BY:(Jenniler Fowles)
Pence Construction,LLC, Daniel Jeffery
Pence Construction,LLC,Eric Wren 11.12"Lam'
Pence Construction, LLC,Jason Stanek 503 252.3802
Pence Construction,LLC,Kurt Schwabauer
Pence Construction,LLC,Franto Sternot
Bassetti Architects P.S.,P.C.,Bassetti Distribution List
Bassetti Architects P.S.,P.C.,Rebecca Walker
Otak,Inc.,Wesley Winship Signed: �/
lei"""Orin/HI
Jennifer Fowles
ADVANCE5i.
--A
Welding & Steel Inc. e4s, - -
VIs Ti''-E6
25,t•wvy 95 N c> GrattgevIll€i.ID 835. !'
P'.208.983.7608^F 208.983.762 f pp ` w
6 1 t .>A..- E/E r Date: 8/6/2020
Page 1 of 3
AUG 1 0 2020 Transmittal#: 12.4
CITY OFTIG Job#: TIG-814
BUQD NG DiVIS O
Tigard High School Modernization
Customer PO#:Neil Bruegeman
Submittal#12.4 Si Stair
To: DSL Builders Attention: Jeff Goodrich
1380 Hines St SE
Salem,OR 97302 Sent Via: Email
We are sending you enclosed, the following:
Erection Drawings
Shop Drawings
Included are I set and 67 prints.
TO BE RETURNED BY:
D A CE.D
Welding & Steel Inc.
QTIrIED
25t Hwy 95 N Gsangsvelie,ID 835 v:
P. 208,983.76080 F:208.983.7
"' Date: 8/6/2020
AUG 1 0 2020 Page 2 of 3
Transmittal#: 12.4
CITY OFTI N;O
BUILDING DIVISION Job#: TIG-814
Tigard High School Modernization
Customer PO#:Neil Bruegeman
Submittal #12.4 SI Stair
Drawing Number Revision Description Date Detailed/Revised
9601,9602 1 12/23/2019
9701 -9703 1 1/7/2020
9704 0 12/20/2019
11001 0 12/20/2019
11002 1 1/7/2020
11003, 11004 0 12/20/2019
11101 0 12/20/2019
11102 1 1/7/2020
11103 0 12/20/2019
11601, 11602 1 1/7/2020
11701 - 11705 1 1/7/2020
11707 0 12/20/2019
11801 - 11806 1 1/7/2020
12601 1 1/7/2020
12701 - 12703 1 1/7/2020
13601 I 1/7/2020
13701, 13702 1 1/7/2020
13703 0 12/20/2019
14601 1 1/7/2020
14701, 14702 1 1/7/2020
16701 - 16703 1 1/7/2020
17601 1 1/7/2020
17701, 17702 0 12/20/2019
18601 1 1/7/2020
18701, 18702 1 1/7/2020
21701,21702 1 1/7/2020
21703 0 12/20/2019
22701,22702 0 12/20/2019
23701,23702 1 1/7/2020
E9001,E9002 0 12/20/2019
Welcing & Steel Inc.
(1 f. iflA LI.
257 - 95 N ;, Gran erlle,ID8� EcEip`"° a€r�
P:208 983 7608 F 206.983.7621� = "
Date: 8/6/2020
AUG 1 0 2020 Page 3 of 3
CITY OF" IGF :D Transmittal#: 12.4
BUILDING DIVISION
Job#: TIG-814
Tigard High School Modernization
Customer PO#:Neil Bruegeman
Submittal #12.4 S1 Stair
E11001, E11002 0 12/20/2019
E12001 0 12/20/2019
E13001 0 12/20/2019
E14001 0 12/20/2019
E16001 0 12/20/2019
E17001 0 12/20/2019
E18001 0 12/20/2019
E21001 0 12/20/2019
E22001 0 12/20/2019
E23001 0 12/20/2019
This material is being transmitted for the purpose listed below:
For Approval
Delaying the return of approved submittals will delay the delivery of materials.
Remarks: Spec Section: 05 12 00
If enclosures are not as noted,please notify at once.
Advanced Welding and Steel,Inc
Copy To: Brian Gennette By:
Neil Bruegeman